If you have received a residential building contract in Australia and are working through the figures, you have almost certainly encountered the term prime cost item - or PC item. For most homeowners this is one of the most confusing elements of the contract, and one of the most financially significant.
Prime cost items are allowances included in a building contract for specific products or fixtures where the exact cost is not yet known at the time the contract is signed. They are one of the primary mechanisms through which the final cost of a building project exceeds the quoted contract price - and understanding exactly how they work, what the risks are and how to manage them effectively can save homeowners tens of thousands of dollars.
This guide explains what prime cost items are in Australian building contracts, how they differ from provisional sums, why they exist, what the risks are, how to assess whether the allowances in your contract are realistic and what you can do to reduce cost uncertainty before you sign. For a complete framework on building your total project budget refer to the BUILTLY guide on Renovation Budget Australia.
What Is a Prime Cost Item?
A prime cost item - also written as PC item or PC allowance - is a specific allowance included in a building contract for the supply of a particular product, fixture or fitting where the final selection and therefore the exact cost has not yet been determined at the time the contract is executed.
The builder includes a nominated dollar amount in the contract for each PC item - representing their estimate of what the product will cost to supply. When the homeowner makes their final selection and the actual cost of the product is known, the PC allowance in the contract is adjusted - if the actual cost is higher than the allowance the homeowner pays the difference, if it is lower the homeowner receives a credit.
Simple example
A building contract includes a PC allowance of $3,000 for kitchen tapware. The homeowner subsequently selects tapware that costs $4,500. The contract price increases by $1,500 - the difference between the PC allowance and the actual cost. If the homeowner selects tapware costing $2,200 the contract price decreases by $800.
The critical point is that PC items represent cost uncertainty - the final project cost will not be known until all PC items are resolved through actual selections.
What Products Are Typically Included as Prime Cost Items?
PC items are most commonly used for products that require homeowner selection - items where the builder cannot fix a specific product cost in the contract because the homeowner has not yet made their choice.
Common PC Items by Category
Kitchen and Bathroom
- Kitchen tapware and sink
- Bathroom tapware - basin, bath, shower
- Toilet suites
- Basins and baths
- Shower screens and bath screens
- Kitchen appliances - oven, cooktop, dishwasher, rangehood
- Bathroom accessories - towel rails, toilet roll holders, mirrors
Floor and Wall Finishes
- Floor tiles - bathroom, laundry, alfresco
- Wall tiles - bathroom, kitchen splashback
- Floor coverings - carpet, timber, hybrid where not specified - refer to the BUILTLY guide on Flooring Cost Australia for detailed cost ranges
Electrical and Lighting
- Light fittings and pendants
- Ceiling fans
External
- Letterbox
- House numbers
- External lighting
Services
- Hot water system
- Air conditioning units where not fully specified
The breadth of PC items in a contract varies considerably between builders. Some builders include only a handful of PC items - for products that genuinely cannot be specified at contract stage. Others include extensive PC item schedules covering dozens of products - which significantly increases the cost uncertainty in the contract.
Prime Cost Items vs Provisional Sums
Prime cost items and provisional sums are both allowances for uncertain costs in a building contract - but they cover different types of uncertainty and work differently.
Prime Cost Items
- Cover the supply cost of specific products where the selection has not yet been made
- The uncertainty is about what the homeowner will choose
- Builder's labour cost to install is typically included separately in the contract
- Adjustment affects only the supply cost of the nominated product
Provisional Sums
- Cover the cost of defined items of work where the full scope or cost cannot be determined
- The uncertainty is about site conditions or unresolved design
- Covers both supply and labour for the item of work
- Adjustment affects the full cost - producing potentially much larger variations
Both PC items and provisional sums represent cost uncertainty that will be resolved during construction - and both are mechanisms through which the final contract cost can differ significantly from the quoted price. For more detail refer to the BUILTLY guide on Provisional Sums in Building Contracts Australia: What They Are and How to Manage Them.
Why Do Prime Cost Items Exist?
PC items exist because some product selections cannot practically be made at the time a building contract is executed - and because homeowners and builders want to proceed with contracting before every product decision is finalised.
There are legitimate reasons for PC items - some products genuinely require the homeowner to see samples, visit showrooms or make choices that take time. A homeowner who has not yet selected their kitchen tapware should not be prevented from signing a building contract because that selection has not been made.
However PC items can also be used strategically by builders to present a lower headline contract price than the project will actually cost - by setting PC allowances at unrealistically low levels. A contract with $2,000 PC allowances for kitchen appliances that the homeowner is likely to replace with $8,000 appliances presents a contract price that is $6,000 lower than the realistic final cost.
This practice - sometimes called low-balling PC items - is not unusual in the residential building industry and is one of the most common mechanisms through which project costs exceed quoted prices. For more detail on spotting these practices refer to the BUILTLY guide on Dodgy Builders in Australia: How to Spot and Avoid Them.
The Financial Risk of Prime Cost Items
The financial risk of PC items is directly proportional to three factors - the number of PC items in the contract, the gap between the PC allowances and realistic market prices and the homeowner's product preferences relative to what the PC allowances will buy.
Number of PC Items
A contract with twenty PC items covering tapware, appliances, tiles, flooring, lighting and other selections contains significantly more cost uncertainty than one with five PC items. More PC items means more variables and more potential for the final cost to diverge from the contract price.
Adequacy of PC Allowances
PC allowances that reflect realistic current market prices for mid-range products create modest uncertainty - if the homeowner selects products near the allowance level the cost variation will be small. PC allowances that are set significantly below realistic market prices create large certain variations - the homeowner will almost certainly pay more than the allowance regardless of their selections.
Homeowner's Preferences
A homeowner with modest product preferences who is comfortable selecting products at or below the PC allowance level will be largely unaffected by PC items. A homeowner with high specification preferences who will consistently select products well above the PC allowance level will face substantial cost increases.
Example of PC Item Cost Escalation
| PC Item | Allowance | Actual | Variation |
|---|---|---|---|
| Kitchen tapware | $800 | $2,200 | +$1,400 |
| Kitchen appliances | $4,000 | $9,500 | +$5,500 |
| Bathroom tapware × 2 | $1,200 | $3,800 | +$2,600 |
| Floor tiles | $3,500 | $6,200 | +$2,700 |
| Light fittings | $2,000 | $4,500 | +$2,500 |
| Hot water system | $1,800 | $3,200 | +$1,400 |
| Total | $13,300 | $29,400 | +$16,100 |
A homeowner who did not understand PC items and assumed the contract price was fixed could face a $16,100 cost increase from PC item adjustments alone - before any variations or provisional sum adjustments. For more detail on construction costs refer to the BUILTLY guide on How Much Does It Cost to Build a House in Australia?
How to Assess Whether PC Allowances Are Realistic
The most important step in managing PC item risk is assessing the adequacy of each PC allowance before signing the contract - not after.
Research Current Market Prices
For each PC item in the contract, research what the allowance will actually buy at current market prices. Visit tile suppliers, tapware showrooms, appliance retailers and lighting stores. What products are available at the PC allowance level? Are they products you would genuinely be satisfied with?
If the PC allowance for kitchen tapware is $800 and your local tapware supplier's mid-range options start at $1,500, you know before signing that you will spend at least $700 more than the allowance on that item.
Ask the Builder to Justify Each Allowance
Ask the builder to explain the basis for each PC allowance. A builder who has set allowances at realistic market prices should be able to point to specific products in the relevant price range. A builder who set allowances at low levels to reduce the headline price will have difficulty justifying them against current market prices.
Compare PC Allowances Across Builders
When comparing quotes from multiple builders, do not compare headline prices alone - compare the PC allowance levels as well. A lower headline price combined with significantly lower PC allowances may represent a higher realistic final cost than a higher headline price with more generous PC allowances.
Use the Total Realistic Cost Approach
Prepare a realistic cost estimate for each PC item based on your research - what you are likely to actually spend given your preferences and the available products. Sum these realistic costs and compare them to the total PC allowances in the contract. The difference represents your minimum expected PC variation - the additional cost you should budget for above the contract price.
How to Reduce Prime Cost Item Risk
The most effective way to reduce PC item risk is to eliminate or reduce the number of PC items by making selections before the contract is signed.
Make Selections Before Contracting
For every PC item you can finalise before signing - visit showrooms, select specific products and ask the builder to substitute the fixed product price for the PC allowance. When a specific product is nominated in the contract at its actual price, the cost uncertainty is eliminated for that item.
This takes more time before contracting - but the investment pays for itself in cost certainty throughout the project. For pre-contract preparation refer to the BUILTLY guide on Builder Preliminary Agreement in Australia: What It Is and What to Check.
Request Upgraded PC Allowances
Where you cannot make specific selections before contracting, negotiate for PC allowances that reflect the specification level you intend to achieve. If you know you will select quality tapware tell the builder you want PC allowances at a level that reflects quality tapware - not entry-level products.
A builder who is confident in their pricing should be willing to set PC allowances at realistic levels. Resistance to increasing PC allowances is itself a signal that the allowances have been deliberately set low - a red flag worth noting.
Include a PC Contingency in Your Budget
Always budget for PC item variations above the contract price. As a rule of thumb add 20 to 40 percent to the total PC allowances in the contract as a contingency - this represents the likely minimum uplift if you have moderate to high product preferences.
For a contract with $30,000 of total PC allowances, budget an additional $6,000 to $12,000 for PC variations.
Managing Prime Cost Items During Construction
Once the contract is signed, PC item management becomes part of the ongoing construction management process.
Make Selections on Time
Delays in making PC item selections - particularly for products with long lead times like imported tiles, custom joinery hardware or specialist appliances - can delay the construction programme. Confirm with your builder the latest date by which each PC selection must be made to avoid programme impacts and make selections promptly.
Get Written Confirmation of Variations
Every time a PC item is resolved - when you make a selection and the actual cost is confirmed - obtain written confirmation of the variation amount before the product is ordered. Do not rely on verbal conversations or promises to "sort it out later." A running PC variation schedule maintained in writing protects both parties.
Track Your Running Cost Total
Maintain a running total of all confirmed PC variations - both positive and negative. This gives you a live view of how the final contract price is evolving relative to the original contract price and allows you to make informed decisions about remaining selections. Include this as part of your building checklist.
Review Final Account Carefully
At the completion of the project the builder will prepare a final account - the total contract price including all variations. Review the PC item adjustments in the final account carefully against your records of agreed variations. Discrepancies between what you understood was agreed and what appears in the final account are not uncommon and should be identified and resolved before the final payment is made.
For more detail on post-construction processes refer to the BUILTLY guide on Practical Completion in Australia: A Complete Guide for Homeowners.
Red Flags in PC Item Schedules
When reviewing a building contract, the following are red flags in the PC item schedule that warrant further investigation:
Very low allowances across multiple items
If multiple PC allowances are set at levels that are clearly insufficient for even entry-level products - for example $500 for a hot water system or $300 for kitchen tapware - the builder is almost certainly low-balling to present a lower headline price.
Unusually large number of PC items
A contract with more than fifteen to twenty PC items contains significant cost uncertainty. A large PC item schedule is sometimes used to present a lower headline price while deferring substantial costs to the selection process.
No separation between supply and install costs
Where a PC item does not clearly separate the supply cost from the installation cost, variations become harder to assess. Confirm with the builder exactly what the PC item covers - supply only, or supply and installation.
Vague product descriptions
PC items described as "bathroom tapware" without specifying a quality level - for example "mid-range" or "as per specification" - give the builder scope to provide entry-level products at the PC allowance level even if the homeowner's expectations are significantly higher.
BUILTLY is building a record of completed Australian homes that credits the builder, designers and trades behind each one.
Frequently Asked Questions
Are prime cost items legally binding in Australian building contracts?
Yes - PC items and their adjustment mechanism are legally binding terms of the building contract. The contract will specify the procedure for resolving PC items - the process for making selections, confirming actual costs and adjusting the contract price. Both the homeowner and the builder are bound by this process, subject to state building and consumer laws. If a dispute arises about a PC item variation - whether the amount claimed is correct or whether the selection was properly authorised - the dispute is resolved under the contract and if necessary through the relevant state building dispute resolution process.
Can I negotiate PC allowances after the contract is signed?
It is very difficult to change PC allowance levels after the contract is executed - the allowances are a term of the signed contract. This is why it is so important to review and if necessary negotiate PC allowances before signing. Once signed the only way to change an allowance is through a formal variation - which requires the builder's agreement. The time to negotiate is before the contract is executed.
What happens if I cannot decide on a PC item selection during construction?
If you cannot make a PC item selection by the required date check the contract's process for overdue selections, and do not assume the builder may choose a product without your approval - or the programme may be affected while your decision is awaited. Delayed selections are one of the most common causes of programme delays and builder-client friction during construction. Making selections promptly - and well before the required date where possible - is one of the most important things a homeowner can do to keep their project on schedule.
How do I know if a PC allowance is fair?
The most reliable way to assess whether a PC allowance is fair is to research current market prices for the type of product the allowance covers. Visit suppliers, check online retailers and get a realistic sense of what the allowance will buy. If the allowance will comfortably purchase a product you would be satisfied with it is fair. If the allowance will only purchase a product significantly below your expectations it should be renegotiated before signing. A builder who refuses to increase demonstrably inadequate PC allowances should be treated with caution.
Is it better to have fewer PC items or more PC items in a building contract?
Fewer PC items is almost always better for the homeowner - because fewer PC items means less cost uncertainty and a contract price that more accurately reflects the final project cost. The ideal is to make as many product selections as possible before contracting and have them specified at fixed prices in the contract rather than as PC allowances. Where PC items are unavoidable, ensure the allowances are set at realistic levels that reflect your actual preferences and the current market for quality products.
Last updated: October 2026