A progress claim is the builder's formal request for payment for work completed to date - the mechanism through which the contract price is paid in instalments as the building progresses from slab to handover. Most homeowners understand that they will make progress payments during construction. Far fewer understand what a progress claim must contain, what their rights are when they receive one, what the timeframes for payment are under state security of payment legislation and what the consequences are of withholding payment without proper basis. This guide explains exactly what a progress claim is, what it should contain, how the process works under both the building contract and state security of payment legislation and what homeowners should do when they receive one.
What is a progress claim?
A progress claim is a formal written claim submitted by the builder to the owner requesting payment for work completed during a specific period - typically a calendar month or a defined construction stage. It is the mechanism through which the contract price is paid progressively as the building is constructed rather than in a single payment at completion.
Progress claims are governed by two overlapping legal frameworks - the building contract, which specifies the payment stages, amounts and process, and state security of payment legislation, which overrides the contract in some respects to provide statutory payment protections for builders and contractors.
Under the building contract, progress payments are typically tied to the completion of defined construction stages - slab, frame, lock-up, fixing, practical completion. Under security of payment legislation, progress claims may be made on a monthly basis regardless of stage completion - giving the builder a statutory right to claim for work completed even if a contractual stage payment trigger has not been reached.
Progress claim components
| Component | What it contains | Why it matters |
|---|---|---|
| Claim amount | The total amount claimed - including GST | The amount the owner must pay if the claim is not disputed |
| Reference date | The date from which the claim period runs - typically the last day of the month | Determines the timeframe for the owner's payment schedule response |
| Work completed description | Description of work completed during the claim period | Allows the owner to verify the claimed work has been performed |
| Contract sum reference | Reference to the contract sum and previous payments - showing the running total | Confirms the claim is consistent with the contract price |
| Variations included | Any approved variations included in the claim - with variation reference numbers | Allows the owner to confirm included variations were properly approved |
| Retention amount | Where the contract provides for retention - the retention amount held and the balance claimed | Confirms retention is being correctly applied |
| Supporting documentation | Photographs, inspection certificates, subcontractor invoices - depending on contract requirements | Supports the claim if disputed |
Security of payment legislation - the critical framework
Security of payment legislation exists in every Australian state and territory - and it significantly affects the rights of both builders and owners in the progress claim process.
What security of payment legislation does
Security of payment legislation gives contractors - including builders - a statutory right to progress payments for construction work. It creates a rapid adjudication process for disputed payment claims that operates outside and alongside the contract dispute resolution process. The legislation is designed to keep money flowing in the construction industry - preventing owners from withholding payment and creating cash flow crises for builders and their subcontractors.
The payment schedule
Under most state security of payment legislation, when a builder submits a progress claim - called a payment claim under the legislation - the owner has a defined period - typically 10 to 15 business days - to respond with a payment schedule. The payment schedule either agrees to pay the claimed amount or identifies the amount the owner proposes to pay and the reasons for any difference.
The critical consequence of not responding
If the owner does not respond to a payment claim with a payment schedule within the required period, the owner becomes liable to pay the full claimed amount - including amounts the owner might otherwise have disputed. This is the most important and most frequently missed aspect of security of payment legislation for homeowners. Receiving a progress claim and not responding formally within the required timeframe can result in a liability for the full claimed amount regardless of whether the work has been completed.
State variations
Security of payment legislation varies by state - the Building Industry Fairness Act 2017 in Queensland, the Building and Construction Industry Security of Payment Act 1999 in NSW, the Building and Construction Industry Security of Payment Act 2002 in Victoria and equivalent legislation in other states. The response timeframes, the adjudication process and the specific requirements differ between states. Confirm the applicable legislation for your state before construction commences.
Progress claim process by state
| State | Legislation | Payment claim name | Response timeframe | What happens if no response |
|---|---|---|---|---|
| Queensland | Building Industry Fairness Act 2017 | Payment claim | 15 business days for standard claims | Owner liable for full claimed amount - adjudication available |
| New South Wales | Building and Construction Industry Security of Payment Act 1999 | Payment claim | 10 business days | Owner liable for full claimed amount - adjudication available |
| Victoria | Building and Construction Industry Security of Payment Act 2002 | Payment claim | 10 business days | Owner liable for full claimed amount - adjudication available |
| Western Australia | Construction Contracts Act 2004 | Payment claim | 14 days | Owner liable for full claimed amount - adjudication available |
| South Australia | Building and Construction Industry Security of Payment Act 2009 | Payment claim | 15 business days | Owner liable for full claimed amount - adjudication available |
What to do when you receive a progress claim
Step 1 - Check the date
Identify the reference date on the claim - this determines when your response period starts. Calculate the response deadline under the applicable state legislation - typically 10 to 15 business days. Mark the deadline in your calendar immediately. Missing this deadline has serious financial consequences.
Step 2 - Review the claim
Review the claim against the building contract - confirm the claimed amount is consistent with the contract's progress payment schedule for the relevant stage. Confirm any variations included in the claim were properly approved in writing before the work was performed. Confirm the work described in the claim has actually been performed - visit the site if necessary.
Step 3 - Respond formally
If you agree with the claim - pay the claimed amount within the payment period. If you dispute any part of the claim - respond with a payment schedule within the required timeframe, identifying the amount you propose to pay and the specific reasons for the difference. The payment schedule must be specific - a general statement that the work is not complete is insufficient.
Step 4 - Seek advice for disputed claims
For any significant disputed progress claim - above $10,000 - seek advice from a construction lawyer or quantity surveyor before issuing your payment schedule. A payment schedule that is defective in form or insufficient in its reasons may not be effective - leaving you liable for the full claimed amount. Understanding the construction programme helps verify whether claimed stages have been reached.
Progress claim review checklist
Progress claim review checklist
- Note the reference date on the progress claim immediately - calculate and record the payment schedule response deadline for your state
- Confirm the claimed amount is consistent with the building contract's progress payment schedule for the relevant stage
- Confirm any variations included in the claim were approved by you in writing before the work was performed - reject any variation included without prior written approval
- Visit the site to confirm the work described in the claim has been performed - do not pay for work not yet completed
- If you have any grounds to dispute the claim - issue a formal written payment schedule within the required timeframe specifying the amount you propose to pay and the specific reasons for the difference
- Do not ignore a progress claim - failure to respond with a payment schedule within the required timeframe has serious financial consequences under security of payment legislation
- For claims that include the practical completion payment - confirm the occupancy certificate is in your possession before releasing the final payment
- Retain all progress claim documents and payment records - they are essential records if disputes arise
Red flags
Red flags in progress claims
- ✕Progress claim does not reference a specific construction stage or describe what work has been performed - the claim is not adequately supported
- ✕Progress claim includes variations that were not approved in writing before the work was performed
- ✕Progress claim is submitted for a stage that has not been completed - the claimed work has not been performed
- ✕Builder requests the final progress payment before the occupancy certificate has been issued
- ✕Builder submits a payment claim without identifying it as a payment claim under the applicable security of payment legislation - may not be a valid statutory payment claim
- ✕Owner ignores a progress claim without issuing a formal payment schedule - creates liability for the full claimed amount
BUILTLY and lasting project records
BUILTLY and lasting project records
Progress claims and payment records form part of the financial history of any construction project - confirming what was paid, when and for what work.
BUILTLY is building a record of completed Australian homes that credits the builder, designers and trades behind each one.
Frequently Asked Questions
What is a progress claim in construction in Australia?
A progress claim is a formal written claim submitted by the builder requesting payment for work completed during a specific period - typically a calendar month or a defined construction stage. It is the mechanism through which the contract price is paid progressively as the building is constructed. Progress claims are governed by both the building contract - which specifies the payment stages - and state security of payment legislation - which provides statutory payment rights and response timeframe obligations. Homeowners must respond to progress claims within the legislated timeframe - typically 10 to 15 business days - or risk becoming liable for the full claimed amount.
What is the difference between a progress claim and a progress payment?
A progress claim is the builder's formal request for payment - the document submitted to the owner claiming a specific amount for work completed. A progress payment is the payment made by the owner in response to the progress claim - either the full claimed amount or the amount agreed or determined through the payment schedule process. The progress claim initiates the payment process. The progress payment is the result of that process.
What happens if I don't respond to a builder's progress claim in Australia?
If you do not respond to a progress claim with a payment schedule within the required timeframe under the applicable state security of payment legislation - typically 10 to 15 business days - you become liable to pay the full claimed amount. This applies even if the work described in the claim has not been completed or if the claim includes unapproved variations. The failure to respond is treated as agreement to pay the claimed amount. This is the most serious consequence of the security of payment legislation for homeowners and one of the most frequently missed obligations. Always respond to progress claims formally and within the required timeframe.
Can I withhold a progress payment if I am not satisfied with the work?
You can dispute a progress claim by issuing a formal payment schedule within the required timeframe - identifying the amount you propose to pay and the specific reasons for any deduction. You cannot simply withhold payment without issuing a formal payment schedule. If you have a genuine dispute about work quality or completion, document it specifically in the payment schedule - a general statement that the work is unsatisfactory is insufficient. For any significant disputed payment claim seek advice from a construction lawyer before issuing your payment schedule.
What is the final progress payment and when should I release it?
The final progress payment - typically 5 percent of the contract sum - is due at practical completion when the occupancy certificate is issued and keys are handed over. You should not release the final payment before the occupancy certificate is in your possession, before all required handover documents have been received and before the defect schedule has been agreed in writing. The final payment is your primary financial leverage to ensure the builder addresses outstanding defects and provides all required documentation. Once it is released that leverage is gone.