Receiving development approval from council is not the end of the planning process, it is the beginning of a conditions management process that can take weeks or months to complete before a construction certificate can be issued and building work can legally commence. Development approvals in Australia are almost always issued with conditions, specific requirements the applicant must satisfy before construction commences, during construction and before the building can be occupied. Most homeowners read the approval notice, note that the DA has been approved and then hand everything to their builder without reading the conditions carefully. This is a mistake that frequently causes delays, unexpected costs and compliance problems. Understanding what the conditions mean, what action each one requires and what the consequences of missing a condition are is essential knowledge for any homeowner who has received a development approval.
What are council approval conditions?
Council approval conditions, also called conditions of consent, are specific requirements attached to a development approval that the applicant must comply with. They are issued by council as part of the notice of determination and are legally binding on the applicant and any subsequent owner of the property.
Conditions are the mechanism through which council manages the impacts of development, requiring the applicant to take specific actions to ensure the development is constructed and used in a way that is safe, compliant and acceptable to the community. Conditions may require the applicant to pay contributions, provide additional documentation, undertake specific construction methods, install specific infrastructure or comply with ongoing use restrictions.
Every development approval is different, the conditions attached to any specific approval depend on the nature of the development, the characteristics of the site and the planning controls applicable to the zone. A new home in a standard residential zone may have 15 to 25 conditions. A multi-dwelling development on a constrained site may have 50 to 100 conditions. All must be read, understood and actioned before the relevant trigger point.
Condition types by timing
| Condition timing | What it means | Common examples | Consequence of non-compliance |
|---|---|---|---|
| Prior to issue of construction certificate, or prior to issue of building permit | Must be satisfied before the certifier can issue the construction certificate, building cannot legally commence without the CC | Pay Section 7.11 contributions, provide drainage design, submit BASIX commitment items, provide acoustic report, submit landscaping plan | CC cannot be issued, construction cannot commence, project delayed |
| Prior to commencement of building work | Must be satisfied before any physical work commences on site | Appoint principal certifier, erect site signage, install sediment and erosion controls, provide construction management plan | Non-compliant commencement, council may issue stop work order |
| During construction | Must be complied with throughout the construction period, ongoing obligation | Restrict construction hours, manage dust and noise, protect specified trees, maintain site security, stage inspections | Council may issue directions or stop work orders, certifier may refuse to issue occupation certificate |
| Prior to issue of occupation certificate | Must be satisfied before the certifier can issue the occupation certificate, building cannot be legally occupied without the OC | Complete landscaping, complete driveway, submit as-built drainage drawings, provide certification of specific elements, pay outstanding contributions | OC cannot be issued, building cannot be legally occupied |
| Ongoing, use conditions | Apply for the life of the development, ongoing obligations of the owner | Maintain landscaping, no further subdivision without approval, retain specific trees, noise restrictions on use | Council can take enforcement action at any time |
Prior to issue of construction certificate, or prior to issue of building permit
What it means: Must be satisfied before the certifier can issue the construction certificate, building cannot legally commence without the CC
Common examples: Pay Section 7.11 contributions, provide drainage design, submit BASIX commitment items, provide acoustic report, submit landscaping plan
Consequence of non-compliance: CC cannot be issued, construction cannot commence, project delayed
Prior to commencement of building work
What it means: Must be satisfied before any physical work commences on site
Common examples: Appoint principal certifier, erect site signage, install sediment and erosion controls, provide construction management plan
Consequence of non-compliance: Non-compliant commencement, council may issue stop work order
During construction
What it means: Must be complied with throughout the construction period, ongoing obligation
Common examples: Restrict construction hours, manage dust and noise, protect specified trees, maintain site security, stage inspections
Consequence of non-compliance: Council may issue directions or stop work orders, certifier may refuse to issue occupation certificate
Prior to issue of occupation certificate
What it means: Must be satisfied before the certifier can issue the occupation certificate, building cannot be legally occupied without the OC
Common examples: Complete landscaping, complete driveway, submit as-built drainage drawings, provide certification of specific elements, pay outstanding contributions
Consequence of non-compliance: OC cannot be issued, building cannot be legally occupied
Ongoing, use conditions
What it means: Apply for the life of the development, ongoing obligations of the owner
Common examples: Maintain landscaping, no further subdivision without approval, retain specific trees, noise restrictions on use
Consequence of non-compliance: Council can take enforcement action at any time
Most common DA conditions and what they require
| Condition | What it requires | Who is responsible | Typical timing |
|---|---|---|---|
| Section 7.11 contribution, NSW | Pay the infrastructure contribution calculated by council | Applicant, owner | Prior to construction certificate |
| BASIX commitments, NSW | Implement all commitments shown on the BASIX certificate in the construction, insulation, water efficiency, solar | Builder, confirmed by certifier | During construction, certified at OC |
| Drainage design | Submit hydraulic engineer's drainage design for council or certifier approval | Hydraulic engineer, engaged by applicant | Prior to construction certificate |
| Erosion and sediment control | Install erosion and sediment controls before any earthworks commence, typically a silt fence and sediment trap | Builder, principal contractor | Prior to commencement |
| Site signage | Erect a sign at the site entrance showing the development approval number, the principal certifier details and emergency contacts | Builder, principal contractor | Prior to commencement |
| Tree protection, specified trees | Install tree protection zones around specified trees before any work commences, maintain throughout construction | Builder, arborist supervision if required | Prior to commencement, maintained during construction |
| Construction hours | Restrict construction activities to specified hours, typically 7am to 5pm Monday to Saturday, no work Sundays or public holidays | Builder, all contractors | During construction |
| Landscaping | Complete all landscaping shown on the approved plans before the occupation certificate is issued | Owner, landscape contractor | Prior to OC |
| Driveway construction | Construct the driveway to council's specification before the occupation certificate is issued | Owner, builder, council approval of driveway design | Prior to OC |
| Acoustic treatment | Install specified acoustic treatment, acoustic fencing, glazing, mechanical ventilation, before occupation | Builder, confirmed by certifier | Prior to OC |
| Contributions, infrastructure | Pay specified infrastructure contributions, roads, drainage, open space | Owner | Prior to CC or prior to OC as specified |
| Heritage conservation, specific requirements | Conduct work to the heritage conservation areas requirements, photographic recording, specific materials, conservation management plan | Owner, heritage consultant | During construction |
Section 7.11 contribution, NSW
What it requires: Pay the infrastructure contribution calculated by council
Who is responsible: Applicant, owner
Typical timing: Prior to construction certificate
BASIX commitments, NSW
What it requires: Implement all commitments shown on the BASIX certificate in the construction, insulation, water efficiency, solar
Who is responsible: Builder, confirmed by certifier
Typical timing: During construction, certified at OC
Drainage design
What it requires: Submit hydraulic engineer's drainage design for council or certifier approval
Who is responsible: Hydraulic engineer, engaged by applicant
Typical timing: Prior to construction certificate
Erosion and sediment control
What it requires: Install erosion and sediment controls before any earthworks commence, typically a silt fence and sediment trap
Who is responsible: Builder, principal contractor
Typical timing: Prior to commencement
Site signage
What it requires: Erect a sign at the site entrance showing the development approval number, the principal certifier details and emergency contacts
Who is responsible: Builder, principal contractor
Typical timing: Prior to commencement
Tree protection, specified trees
What it requires: Install tree protection zones around specified trees before any work commences, maintain throughout construction
Who is responsible: Builder, arborist supervision if required
Typical timing: Prior to commencement, maintained during construction
Construction hours
What it requires: Restrict construction activities to specified hours, typically 7am to 5pm Monday to Saturday, no work Sundays or public holidays
Who is responsible: Builder, all contractors
Typical timing: During construction
Landscaping
What it requires: Complete all landscaping shown on the approved plans before the occupation certificate is issued
Who is responsible: Owner, landscape contractor
Typical timing: Prior to OC
Driveway construction
What it requires: Construct the driveway to council's specification before the occupation certificate is issued
Who is responsible: Owner, builder, council approval of driveway design
Typical timing: Prior to OC
Acoustic treatment
What it requires: Install specified acoustic treatment, acoustic fencing, glazing, mechanical ventilation, before occupation
Who is responsible: Builder, confirmed by certifier
Typical timing: Prior to OC
Contributions, infrastructure
What it requires: Pay specified infrastructure contributions, roads, drainage, open space
Who is responsible: Owner
Typical timing: Prior to CC or prior to OC as specified
Heritage conservation, specific requirements
What it requires: Conduct work to the heritage conservation areas requirements, photographic recording, specific materials, conservation management plan
Who is responsible: Owner, heritage consultant
Typical timing: During construction
How to read a notice of determination
A notice of determination is the formal document issued by council confirming the outcome of the DA assessment. Reading it correctly, understanding its structure and identifying the conditions that require action, is the first practical step after receiving DA approval.
The determination notice structure
The notice of determination typically begins with a summary, the property address, the DA number, the development description and the determination, approved, approved with modifications or refused. If approved the notice will state whether it is approved with or without conditions.
Following the summary is the list of conditions, typically numbered sequentially and grouped by timing. The most critical conditions to identify first are those in the prior to construction certificate category, these are the conditions that must be satisfied before the certifier can issue the CC and before any building work can commence.
Standard conditions vs site-specific conditions
Most councils use standard condition templates for common requirements, tree protection, erosion control, construction hours, site signage. These standard conditions are applied to most DAs and their requirements are well-established. Site-specific conditions, conditions written specifically for the characteristics of a particular site, are typically more complex and may require specialist advice to interpret and comply with. Read site-specific conditions carefully and seek advice where the requirement is not immediately clear.
The legal description vs the practical requirement
Conditions are written in legal language that describes the outcome required, not always the specific action needed to achieve it. A condition that states the applicant shall provide a detailed stormwater management plan prepared by a qualified engineer prior to the issue of the construction certificate tells you the outcome required, a stormwater management plan, but not the specific technical content the plan must address. Understanding the practical requirement behind the legal description of each condition is the key skill in reading a conditions schedule.
Prior to construction certificate conditions, the most critical
The prior to construction certificate conditions are the most time-critical conditions in any approval, they must be satisfied before the certifier can issue the construction certificate and before any building work can legally commence. Missing or mismanaging these conditions is the most common cause of construction commencement delays.
Section 7.11 contributions
In NSW Section 7.11 infrastructure contributions are typically a prior to CC condition. The contribution amount is calculated by council based on the development contribution plan applicable to the area and the nature of the development. Contributions for a new residential dwelling in a metropolitan council area can range from $5,000 to $40,000 or more. Confirm the contribution amount early, it is a significant cost that must be budgeted and paid before the CC is issued.
Engineering designs
Many DAs require hydraulic engineering designs, geotechnical assessments or other technical documentation to be prepared and approved before the CC is issued. These designs take time to prepare and approve, engage the relevant consultants immediately after receiving the DA approval rather than waiting until the builder is ready to commence.
BASIX commitment schedules, NSW
The BASIX certificate attached to the DA specifies the energy and water efficiency commitments that must be implemented in the construction. The construction certificate application must demonstrate that the construction documentation incorporates all BASIX commitments. Confirm with the architect that all BASIX commitments are reflected in the CC drawings before submitting. See the guide on NatHERS rating for more on energy efficiency requirements.
During construction conditions, managing ongoing compliance
During construction conditions are the builder's ongoing obligations throughout the construction period. They require active management, not just compliance at a single point in time. Refer to the construction timeline to understand how these obligations fit within the broader programme.
Construction hours
Construction hours conditions specify the permitted times for noisy construction activities, typically 7am to 5pm Monday to Friday, 7am to 1pm Saturday and no work on Sundays or public holidays. Confirm with the builder that all subcontractors are aware of the construction hours and that the site supervisor is responsible for enforcing them. Breaches of construction hours conditions are a common source of neighbour complaints and council enforcement action.
Tree protection
Tree protection conditions require the installation and maintenance of tree protection zones around specified trees throughout the construction period. The tree protection zone typically consists of a temporary fence erected at the drip line of the tree, the outer edge of the canopy, that prevents machinery, materials storage and vehicle access within the root zone. Confirm with the builder that tree protection is installed before any site clearing commences and that it is maintained throughout the construction programme.
Stage inspections
Some DA conditions require specific inspections to be conducted during construction, in addition to the mandatory building certifier inspections. Heritage conservation conditions may require a heritage consultant to inspect specific elements before they are concealed. Acoustic conditions may require acoustic consultant certification of specific installations. Tree conditions may require an arborist to inspect tree protection at specified stages. Identify all inspection requirements at the start of construction and schedule them in the construction programme.
Prior to occupation certificate conditions, the final hurdle
Prior to occupation certificate conditions must be satisfied before the certifier can issue the occupation certificate, the document that confirms the building is legally approved for occupation. Missing a prior to OC condition means the OC cannot be issued and the building cannot be legally occupied.
Landscaping
Landscaping conditions are one of the most common prior to OC conditions and one of the most commonly missed. The condition typically requires all landscaping shown on the approved landscape plan to be installed before the OC is issued. This means the landscaping must be complete, plants installed, mulch laid, irrigation operational, before the certifier will issue the OC. Plan the landscaping programme to be complete before the building itself is finished, not after.
Driveway
Driveway construction conditions require the driveway, typically the kerb crossover and the driveway from the street to the garage, to be constructed to council's specification before the OC is issued. The kerb crossover is typically constructed by council or an approved contractor to council's specifications. Confirm the kerb crossover approval and construction timeline with council early in the project.
Outstanding contributions
Some contributions are payable prior to the OC rather than prior to the CC. Confirm the payment timing for each contribution condition at the start of the project.
Conditions management checklist
Read every condition in the notice of determination immediately after receiving the DA approval, do not hand it to the builder without reading it yourself
Create a conditions register, a table listing every condition, its timing, what action is required, who is responsible and the current status
Identify all prior to construction certificate conditions, these are the most time-critical, and commence actioning them immediately
Confirm the Section 7.11 contribution amount and payment timing, budget for it before signing the building contract
Engage required consultants, hydraulic engineer, acoustic consultant, heritage consultant, immediately after DA approval, do not wait until the builder is ready to start
Brief the builder on all during construction conditions before the construction programme is finalised, construction hours, tree protection, site signage, erosion controls
Confirm all prior to commencement conditions, site signage, sediment controls, principal certifier appointment, are satisfied before any earthworks or building work commences
Include prior to OC conditions in the construction programme, landscaping and driveway must be scheduled to be complete before the building is finished
Confirm the certifier has received evidence of compliance for every prior to CC condition before submitting the CC application
After the OC is issued, review any ongoing use conditions and confirm the owner is aware of their ongoing obligations
Red flags
- •Builder commences work before all prior to CC conditions have been satisfied, particularly before the construction certificate has been issued, this is illegal
- •Section 7.11 contribution has not been budgeted, can be a significant cost that is payable before construction can commence
- •Engineering designs required as prior to CC conditions have not been commissioned, project delays likely
- •Landscaping condition not identified until handover, landscaping cannot be completed before the OC is issued, occupation delayed
- •Tree protection conditions not briefed to the builder, protected trees damaged during construction, council enforcement action possible
- •Ongoing use conditions not read, owner unknowingly breaches ongoing conditions after occupation
- •Conditions schedule has not been shared with the builder, builder unaware of during construction obligations
BUILTLY and lasting project records
BUILTLY is building a record of completed Australian homes that credits the builder, designers and trades behind each one.
Frequently asked questions
What are council approval conditions in Australia?
Council approval conditions, conditions of consent, are specific requirements attached to a development approval that the applicant must comply with. They are legally binding and cover a range of requirements, paying infrastructure contributions, providing engineering designs, implementing specific construction methods, completing landscaping and complying with ongoing use restrictions. Conditions are grouped by timing, prior to construction certificate, prior to commencement, during construction, prior to occupation certificate and ongoing. All conditions must be read carefully and actioned at the correct timing, missing a condition can prevent the construction certificate or occupation certificate from being issued.
What happens if I don't comply with DA conditions in Australia?
Non-compliance with conditions of consent can have serious consequences depending on which condition has not been met. If a prior to construction certificate condition has not been satisfied the certifier cannot issue the construction certificate and building work cannot legally commence. If a prior to occupation certificate condition is not satisfied the OC cannot be issued and the building cannot be legally occupied. During construction non-compliance can result in council issuing directions or a stop work order. For ongoing use conditions council can take enforcement action at any time. Non-compliance with conditions can also affect the validity of the development consent itself.
How do I know what each DA condition requires in Australia?
Read each condition carefully and identify the specific outcome required, the document to be provided, the action to be taken or the standard to be achieved. For standard conditions, construction hours, erosion control, site signage, the requirement is typically straightforward. For site-specific conditions involving technical requirements, drainage design, acoustic treatment, heritage conservation, seek advice from the relevant specialist before attempting to comply. If a condition is unclear contact council's development assessment team and ask for clarification in writing, verbal clarifications are not reliable.
What is a Section 7.11 contribution and when is it paid in NSW?
A Section 7.11 contribution, previously called a Section 94 contribution, is an infrastructure contribution payable to council by a developer or homeowner as a condition of development approval in NSW. The contribution funds council infrastructure, roads, drainage, open space, community facilities, that the new development places additional demand on. The contribution amount is calculated under the council's contributions plan and varies by council and development type. For a new residential dwelling in a metropolitan council area contributions can range from $5,000 to $40,000 or more. The contribution is typically payable prior to the issue of the construction certificate, confirm the timing in the conditions of consent.
Who is responsible for complying with DA conditions, the owner or the builder?
Both, and the responsibility depends on which condition and which timing. Prior to construction certificate conditions are typically the owner's responsibility, paying contributions, engaging consultants and providing designs. Prior to commencement and during construction conditions are typically the builder's responsibility, erecting site signage, installing erosion controls, managing construction hours and tree protection. Prior to occupation certificate conditions are shared, the owner is responsible for landscaping and contributions, the builder is responsible for completing construction elements. Ongoing use conditions are the owner's responsibility throughout the life of the property. Confirm the responsibility allocation with the builder before construction commences.