Soil Testing and Classification in Australia: A Complete Guide

Last updated: October 2026

Before any residential construction project in Australia, the ground beneath the proposed building needs to be understood. A soil test, formally called a geotechnical investigation, determines the composition and reactivity of the soil on your site and produces a soil classification under Australian Standard AS 2870. That classification then determines how your home's footing system must be designed, what it will cost and how much structural risk the site carries. Skipping or delaying the soil test is one of the most commonly made and most costly mistakes in residential construction, leading to under-engineered footings, expensive variations during construction and in the worst cases, structural cracking years after the home is complete. This guide explains what a soil test involves, what it costs, what the classification results mean and what to do with the information. For a detailed breakdown of the classification system itself, see our companion guide to soil classification in Australia.

What is a soil test?

A soil test, or geotechnical investigation, is a site-specific assessment of the soil conditions beneath a proposed building. It is conducted by a geotechnical engineer or geotechnical testing company and involves drilling or excavating test holes or borings to extract soil samples at defined depths, laboratory testing of the samples to determine clay mineral content, plasticity index and other relevant properties, and preparation of a geotechnical report including the AS 2870 soil classification for the site.

The soil test report is used by the structural engineer to design the footing system, the slab type, beam depth, reinforcement layout and any additional engineering measures required for the specific site conditions. Without a soil test, the structural engineer must assume a classification, typically Class M, which may or may not be correct for the actual site.

A soil test is not the same as a soil survey. A soil survey is a broader landscape assessment. A geotechnical investigation is specifically focused on the engineering properties of the soil relevant to building design.

Why soil testing matters before building

The soil classification determined by the test has a direct and substantial effect on three things that every homeowner and developer cares about.

Footing design. The structural engineer uses the soil classification to design the footing system. A footing system designed for the wrong classification is either over-engineered and wasteful, money spent on unnecessary structural robustness, or under-engineered and at risk of failure. Under-engineered footings on reactive clay sites are among the most common causes of structural cracking in Australian residential buildings. Understanding how the structural engineer evaluates and responds to site conditions is essential.

Construction cost. Higher soil classifications require more substantial footing systems, more concrete, more reinforcement, deeper beams. The cost difference between a Class M footing and a Class H2 or Class E footing on the same house can be $10,000 to $50,000 or more depending on the house size and the specific engineering response required. Discovering this after the building contract is signed, through a provisional sum that has been exceeded, is significantly more disruptive than pricing it correctly from the outset. See our guide to the cost to build a house in Australia for the full picture.

Long-term structural performance. A home built on a correctly engineered footing for its soil classification performs structurally over its full design life. A home built on an under-engineered footing on reactive clay will show cracking, in the slab, in internal walls, in door and window frames, as the soil moves through seasonal wet and dry cycles. Rectifying structural cracking caused by inadequate footings is expensive, disruptive and in some cases impossible without complete footing replacement.

Types of soil tests and what they cost

Test typeWhat it involvesTypical costWhen it is used
Standard residential soil testTwo to three hand auger or machine bored test holes to 2 to 3 metres depth, laboratory testing, AS 2870 classification report$800 to $2,000Standard residential new home on a site with no known unusual conditions
Extended residential soil testThree to five test holes to greater depth, additional laboratory testing, more detailed report$1,500 to $3,500Sites with variable conditions, sloped sites, larger floor plates, sites adjacent to trees
Geotechnical investigation, complex siteMultiple test holes to significant depth, groundwater assessment, acid sulfate soil assessment, detailed engineering report$3,000 to $8,000+Problem sites, Class P classification likely, contamination suspected, waterway-adjacent sites, significant slope
Acid sulfate soil assessmentSpecific testing for acid sulfate soil conditions in addition to standard classification$500 to $2,000 additionalCoastal and estuarine sites in Queensland, NSW and Victoria where acid sulfate soils are likely
Contamination assessmentSoil sampling and laboratory testing for chemical contamination$2,000 to $10,000+Former industrial, commercial or service station sites, sites with visible contamination indicators

Test type

Standard residential soil test

What it involves

Two to three hand auger or machine bored test holes to 2 to 3 metres depth, laboratory testing, AS 2870 classification report

Typical cost

$800 to $2,000

When it is used

Standard residential new home on a site with no known unusual conditions

Test type

Extended residential soil test

What it involves

Three to five test holes to greater depth, additional laboratory testing, more detailed report

Typical cost

$1,500 to $3,500

When it is used

Sites with variable conditions, sloped sites, larger floor plates, sites adjacent to trees

Test type

Geotechnical investigation, complex site

What it involves

Multiple test holes to significant depth, groundwater assessment, acid sulfate soil assessment, detailed engineering report

Typical cost

$3,000 to $8,000+

When it is used

Problem sites, Class P classification likely, contamination suspected, waterway-adjacent sites, significant slope

Test type

Acid sulfate soil assessment

What it involves

Specific testing for acid sulfate soil conditions in addition to standard classification

Typical cost

$500 to $2,000 additional

When it is used

Coastal and estuarine sites in Queensland, NSW and Victoria where acid sulfate soils are likely

Test type

Contamination assessment

What it involves

Soil sampling and laboratory testing for chemical contamination

Typical cost

$2,000 to $10,000+

When it is used

Former industrial, commercial or service station sites, sites with visible contamination indicators

What causes soil reactivity

Understanding why soils react the way they do helps homeowners understand why the classification matters and what can change the effective reactivity of a site over time.

Clay mineral content. Reactive clays contain specific clay minerals, primarily montmorillonite and smectite, that absorb water molecules, causing the clay particles to expand significantly. The higher the concentration of these minerals, the more reactive the soil.

Moisture change. Reactivity is driven by moisture change, not by moisture content alone. A clay site that stays consistently wet or consistently dry has limited movement. A clay site that cycles between wet and dry conditions, as most Australian residential sites do through seasonal variation, experiences the expansion and contraction that creates structural risk.

Tree roots and vegetation. Large trees extract significant moisture from surrounding soil, creating localised drying and shrinkage that can cause differential movement under footings. Removing a large tree near an existing footing causes the reverse, rehydration and expansion. Both scenarios cause structural movement.

Drainage and water management. Poor site drainage that allows water to pond near the building can cause localised wetting and expansion. Leaking pipes under or near the slab produce similar effects. Good drainage design is an important maintenance consideration on reactive sites.

Landscaping and irrigation. Garden beds against the house that are regularly watered, lawn irrigation systems and paving that directs water toward the building can all increase moisture variation under the footing, increasing the effective reactivity of the site beyond what the classification assumed at the time of testing.

Soil classification classes explained

For a detailed breakdown of each classification, see our dedicated guide to soil classification in Australia.

ClassNameSoil behaviourExpected surface movementFooting system required
Class AStable, non-reactiveSand, rock or dry areas with minimal moisture changeLess than 20mmStandard footing, lowest cost
Class SSlightly reactiveClay soils with slight reactivity20 to 40mmLight footing, minor additional reinforcement
Class MModerately reactiveMedium clay or silt soils40 to 60mmStandard reactive clay footing, most common in Australian capital cities
Class H1Highly reactiveHigh clay content soils60 to 75mmMore robust footing, deeper beams, additional reinforcement
Class H2Highly reactiveVery high clay content soils75 to 100mmSignificantly more robust footing, substantial cost premium
Class EExtremely reactiveExtremely high clay content or problem soilsGreater than 100mmEngineered solution required, significant cost premium
Class PProblem siteFilled sites, soft soils, collapsing soils, waterlogged sites, highly variable soilsVariable and potentially severeIndividual engineering solution required, most expensive

Class

Class A

Name

Stable, non-reactive

Soil behaviour

Sand, rock or dry areas with minimal moisture change

Expected surface movement

Less than 20mm

Footing system required

Standard footing, lowest cost

Class

Class S

Name

Slightly reactive

Soil behaviour

Clay soils with slight reactivity

Expected surface movement

20 to 40mm

Footing system required

Light footing, minor additional reinforcement

Class

Class M

Name

Moderately reactive

Soil behaviour

Medium clay or silt soils

Expected surface movement

40 to 60mm

Footing system required

Standard reactive clay footing, most common in Australian capital cities

Class

Class H1

Name

Highly reactive

Soil behaviour

High clay content soils

Expected surface movement

60 to 75mm

Footing system required

More robust footing, deeper beams, additional reinforcement

Class

Class H2

Name

Highly reactive

Soil behaviour

Very high clay content soils

Expected surface movement

75 to 100mm

Footing system required

Significantly more robust footing, substantial cost premium

Class

Class E

Name

Extremely reactive

Soil behaviour

Extremely high clay content or problem soils

Expected surface movement

Greater than 100mm

Footing system required

Engineered solution required, significant cost premium

Class

Class P

Name

Problem site

Soil behaviour

Filled sites, soft soils, collapsing soils, waterlogged sites, highly variable soils

Expected surface movement

Variable and potentially severe

Footing system required

Individual engineering solution required, most expensive

The critical H1 vs H2 distinction: Both are classified as highly reactive but H2 sites have greater expected surface movement and require a substantially more robust engineering response. Using an H1 footing specification on an H2 site is under-engineering the foundation, a defect that may not manifest for years but causes significant structural cracking when seasonal moisture variation creates the full extent of movement the site is capable of.

Class P is the classification applied to sites that do not fit the standard reactive clay framework, filled sites, soft or compressible soils, sites subject to inundation, highly variable sites and any site with conditions that fall outside the other classifications. Class P requires an individual engineering solution with no standard footing system applicable.

Soil classification by location in Australia

Understanding your area's typical soil conditions is a useful starting point, but a site-specific test is always required. If you are choosing a builder in a specific city, our location-specific guides cover local soil considerations: Melbourne, Sydney.

LocationDominant soil typeTypical classificationKey notes
Sydney eastern suburbs and lower north shoreHawkesbury SandstoneClass A to Class SRock or sandy soil, low reactivity. Footing into rock common
Sydney inner west, south and southwestClayClass M to Class H1Reactivity increases further west
Sydney hills district and outer westReactive clayClass H1 to Class H2Some of the most reactive soils in the Sydney basin
Melbourne inner suburbsBasalt and clayClass M to Class H1Variable, some rock, some reactive clay
Melbourne southeast, eastern and outer suburbsReactive clayClass H1 to Class H2Among the most reactive residential soils in Australia
Melbourne western suburbsBasalt rock and clayClass A to Class H1Variable, basalt rock in some areas, reactive clay in others
Brisbane north and inner suburbsWeathered rock and clayClass M to Class H1Variable by suburb
Brisbane south and southwestReactive clayClass H1 to Class H2Higher reactivity than inner Brisbane
Gold Coast coastal plainSand and alluvialClass A to Class S coastal, Class P possible near waterwaysSandy coastal soils low reactivity, canal-front sites may have soft alluvial Class P conditions
Perth coastal plain, Bassendean SandSandClass AVery low reactivity, low bearing capacity requires engineered footings despite low reactivity
Perth limestone ridgeTamala LimestoneClass A, but requires drillingRock footing common, low reactivity but specialist drilling required
Perth eastern suburbs and hillsClayClass M to Class H1Reactivity increases further east
Adelaide plainsClayClass H1 to Class H2Highly reactive soils across significant parts of the Adelaide plains
CanberraClay and graniteClass M to Class H2Cold climate increases moisture variation, reactive clay performance can be more severe

Location

Sydney eastern suburbs and lower north shore

Dominant soil type

Hawkesbury Sandstone

Typical classification

Class A to Class S

Key notes

Rock or sandy soil, low reactivity. Footing into rock common

Location

Sydney inner west, south and southwest

Dominant soil type

Clay

Typical classification

Class M to Class H1

Key notes

Reactivity increases further west

Location

Sydney hills district and outer west

Dominant soil type

Reactive clay

Typical classification

Class H1 to Class H2

Key notes

Some of the most reactive soils in the Sydney basin

Location

Melbourne inner suburbs

Dominant soil type

Basalt and clay

Typical classification

Class M to Class H1

Key notes

Variable, some rock, some reactive clay

Location

Melbourne southeast, eastern and outer suburbs

Dominant soil type

Reactive clay

Typical classification

Class H1 to Class H2

Key notes

Among the most reactive residential soils in Australia

Location

Melbourne western suburbs

Dominant soil type

Basalt rock and clay

Typical classification

Class A to Class H1

Key notes

Variable, basalt rock in some areas, reactive clay in others

Location

Brisbane north and inner suburbs

Dominant soil type

Weathered rock and clay

Typical classification

Class M to Class H1

Key notes

Variable by suburb

Location

Brisbane south and southwest

Dominant soil type

Reactive clay

Typical classification

Class H1 to Class H2

Key notes

Higher reactivity than inner Brisbane

Location

Gold Coast coastal plain

Dominant soil type

Sand and alluvial

Typical classification

Class A to Class S coastal, Class P possible near waterways

Key notes

Sandy coastal soils low reactivity, canal-front sites may have soft alluvial Class P conditions

Location

Perth coastal plain, Bassendean Sand

Dominant soil type

Sand

Typical classification

Class A

Key notes

Very low reactivity, low bearing capacity requires engineered footings despite low reactivity

Location

Perth limestone ridge

Dominant soil type

Tamala Limestone

Typical classification

Class A, but requires drilling

Key notes

Rock footing common, low reactivity but specialist drilling required

Location

Perth eastern suburbs and hills

Dominant soil type

Clay

Typical classification

Class M to Class H1

Key notes

Reactivity increases further east

Location

Adelaide plains

Dominant soil type

Clay

Typical classification

Class H1 to Class H2

Key notes

Highly reactive soils across significant parts of the Adelaide plains

Location

Canberra

Dominant soil type

Clay and granite

Typical classification

Class M to Class H2

Key notes

Cold climate increases moisture variation, reactive clay performance can be more severe

These are indicative ranges only. Soil conditions vary at suburb and lot level. A site-specific geotechnical investigation is always required.

Footing cost premium by soil classification

Soil classTypical footing systemApproximate cost premium over Class ANotes
Class ASimple strip footing or standard slabBaseline, no premiumSand, rock or non-reactive soil
Class SSlightly reinforced slab$2,000 to $5,000Minor additional reinforcement
Class MWaffle pod slab or reinforced strip footing$5,000 to $15,000Standard reactive clay response, most common in capital cities
Class H1Stiffened raft slab with deeper edge beams$15,000 to $30,000More substantial beam depth and reinforcement
Class H2Heavily stiffened raft slab with significantly deeper beams$25,000 to $50,000Significant engineering response required
Class EIndividual engineering design, typically deep strip footings or piers$40,000 to $100,000+Highly variable depending on specific site conditions
Class PIndividual engineering design, piers, piles or engineered slab$30,000 to $150,000+Most variable, filled sites and waterway-adjacent sites highest variability

Soil class

Class A

Typical footing system

Simple strip footing or standard slab

Approximate cost premium over Class A

Baseline, no premium

Notes

Sand, rock or non-reactive soil

Soil class

Class S

Typical footing system

Slightly reinforced slab

Approximate cost premium over Class A

$2,000 to $5,000

Notes

Minor additional reinforcement

Soil class

Class M

Typical footing system

Waffle pod slab or reinforced strip footing

Approximate cost premium over Class A

$5,000 to $15,000

Notes

Standard reactive clay response, most common in capital cities

Soil class

Class H1

Typical footing system

Stiffened raft slab with deeper edge beams

Approximate cost premium over Class A

$15,000 to $30,000

Notes

More substantial beam depth and reinforcement

Soil class

Class H2

Typical footing system

Heavily stiffened raft slab with significantly deeper beams

Approximate cost premium over Class A

$25,000 to $50,000

Notes

Significant engineering response required

Soil class

Class E

Typical footing system

Individual engineering design, typically deep strip footings or piers

Approximate cost premium over Class A

$40,000 to $100,000+

Notes

Highly variable depending on specific site conditions

Soil class

Class P

Typical footing system

Individual engineering design, piers, piles or engineered slab

Approximate cost premium over Class A

$30,000 to $150,000+

Notes

Most variable, filled sites and waterway-adjacent sites highest variability

When to commission a soil test

Before design commences is the ideal timing, so the structural engineer can design the footing system for the correct soil classification from the outset. This eliminates the most common and avoidable cost variation in residential construction.

Before signing the building contract is the minimum acceptable timing. If the soil test is completed before contract signing, the contract price can reflect the actual footing requirement for the site's soil classification rather than an assumed or standard specification. This eliminates the provisional sum variation that discovers a higher-than-assumed classification after the contract is signed. Our guide to building a house checklist covers the full timeline.

Never after construction commences. A soil test conducted after the slab is poured tells you what classification the footing was probably inadequate for, not useful information at that stage.

For knockdown rebuild projects, the existing soil test from the original construction, if available, provides useful context but should be supplemented with a current investigation, particularly if significant changes have occurred on the site since the original test.

How to read your soil test report

Confirm the AS 2870 soil classification is clearly stated, Class A, S, M, H1, H2, E or P

Confirm the report is site-specific, prepared for your specific lot address based on test holes conducted on your site

Check the number and depth of test holes, a single shallow test hole may not be representative of the full site

Check for any additional site conditions noted, groundwater, acid sulfate soils, fill material, tree root influence or other factors beyond the basic classification

Provide the report to the structural engineer immediately, confirm the structural engineer has used the classification to design the footing system before the footing design is finalised

Confirm whether the classification is uniform across the site or variable, variable classifications may require additional investigation in specific areas

Check the report date, a soil test conducted more than two to three years before construction may not reflect current conditions if significant vegetation changes, fill or drainage works have occurred since the test

Retain the report permanently, it is a critical document for future renovation, insurance claims and property resale

Soil testing and the building contract

The soil classification has a direct financial relationship with the building contract. Volume builders frequently include a standard footing specification, typically designed for Class M conditions, with a provisional sum for site conditions. If the soil test reveals a higher classification, the provisional sum is exceeded and the homeowner pays the difference as a variation.

This is one of the most common and avoidable cost surprises in residential construction. Eliminating it requires three steps:

  1. Commission the soil test before the building contract is signed
  2. Confirm the contract footing specification matches the actual soil classification
  3. Eliminate or minimise the provisional sum for site conditions by pricing the actual footing requirement

For custom homes, the structural engineer designs the footing system from the soil test result and the building contract price reflects the actual footing design, not an assumed standard specification. Understanding how to choose a builder includes confirming they handle soil classification correctly.

Red flags relating to soil testing

Red flags to watch for

  • Builder proposes a standard footing specification without confirming the soil classification first
  • Soil test has not been conducted before the building contract is signed, provisional sum used instead of actual footing specification
  • Volume builder includes a very low provisional sum for site conditions, insufficient to cover an H1 or H2 footing on a reactive clay site
  • Single shallow test hole used on a large or irregular site, inadequate investigation for site variability
  • Structural engineer has not been provided with the soil test report before designing the footing system
  • Builder proceeds to slab pour before the soil test result is received and the structural engineer has confirmed the footing design
  • No mention of groundwater, acid sulfate soils or fill on sites where these are likely
  • Soil test was conducted by the builder's preferred company with results that appear more favourable than neighbouring properties, independent verification may be warranted
  • Builder is unaware of the soil classification applicable to your site despite it being available

BUILTLY and lasting project records

Soil classification is one of the most practically important pieces of site-specific information for any completed home, and one of the least likely to be preserved after construction is complete. A future owner, renovator or insurer who knows the soil classification of a property can make informed decisions about structural modifications, landscaping and maintenance.

BUILTLY is building a record of completed Australian homes that credits the builder, architects, designers and trades behind each one.

BUILTLY is building a record of completed Australian homes that credits the builder, architects, designers and trades behind each one.

Frequently asked questions

What is a soil test in Australia and why do I need one?

A soil test, formally called a geotechnical investigation, is a site-specific assessment of the soil conditions beneath your proposed building. It involves drilling test holes, extracting soil samples and laboratory testing to determine the AS 2870 soil classification for your site. The classification determines how the structural engineer must design your footing system, the slab type, beam depth and reinforcement required to safely manage the soil's movement characteristics. Without a soil test, the footing system is designed on an assumed classification that may be incorrect for your site, leading to under-engineered footings, expensive variations during construction or structural cracking years after completion.

How much does a soil test cost in Australia?

A standard residential soil test in Australia typically costs $800 to $2,000 depending on the number of test holes required, the investigation depth and the location. Extended investigations for sites with variable conditions or complex soil profiles typically cost $1,500 to $3,500. Complex sites, problem soils, waterway-adjacent, contamination suspected, require more extensive geotechnical investigation costing $3,000 to $8,000 or more. A soil test is among the most cost-effective investigations available relative to the financial risk it manages, the cost of discovering a Class H2 site after the building contract is signed typically exceeds the soil test cost by 20 times or more.

What do the soil classification classes mean in Australia?

Australian soil classifications under AS 2870 describe the reactivity of the soil, its tendency to expand and contract with moisture change. Class A is stable and non-reactive, sand or rock requiring a standard footing. Class S is slightly reactive. Class M is moderately reactive, the most common classification in Australian capital cities, requiring a waffle pod or reinforced slab. Class H1 and H2 are highly reactive, requiring increasingly robust stiffened raft slab systems. Class E is extremely reactive, requiring individual engineering solutions. Class P covers problem sites, filled, soft, waterlogged or highly variable, also requiring individual engineering solutions and typically the most expensive footing outcome.

When should I get a soil test done?

Before design commences is ideal, so the structural engineer can design the footing system for the correct classification from the outset. Before signing the building contract is the minimum acceptable timing, it allows the contract price to reflect the actual footing requirement rather than an assumed standard specification with a provisional sum that may be significantly exceeded. A soil test commissioned after the building contract is signed but before the slab is poured can still prevent under-engineering, but may require variations to the contract. A soil test after the slab is poured provides information that is no longer actionable for the current project.

What happens if my soil test reveals a Class H2 or Class P result?

A Class H2 or Class P result means the footing system must be more robustly engineered than a standard residential slab. For Class H2 the structural engineer designs a heavily stiffened raft slab with significantly deeper edge beams and additional reinforcement, adding approximately $25,000 to $50,000 to footing costs above a Class A baseline. For Class P the engineer designs an individual solution, piers, piles or a specially engineered slab, with costs ranging from $30,000 to $150,000 or more depending on the specific site conditions. These are real costs that must be budgeted. Discovering them after the building contract is signed through a provisional sum variation is significantly more disruptive than pricing them correctly from a pre-contract soil test.