Easements on Property in Australia: What They Mean Before You Build

Last updated: October 2026

An easement on a property title is one of the most practically significant encumbrances a homeowner or developer can encounter, and one of the most commonly discovered too late. An easement gives another party a legal right to use part of your land for a specific purpose, a drainage easement allowing the council to maintain underground pipes, a right of way giving a neighbour access across your land, a services easement protecting underground utilities. The presence of an easement does not prevent you from buying or building, but it can significantly restrict what you can build, where you can build it and what you can do with the land above and around it. Understanding what easements are, how to find them and what they mean for your construction project is essential due diligence, as part of the broader pre-construction stage, for any homeowner or developer in Australia.

What is an easement?

An easement is a legal right registered on a property title that gives a person or organisation, called the easement holder or dominant tenement, the right to use part of another person's land, called the burdened or servient tenement, for a specific, defined purpose.

The easement is attached to the land, not to the owner. When a property is sold, the easement transfers with the title to the new owner. The new owner takes the property subject to the easement, they cannot remove it simply by purchasing the property.

Easements in Australia are registered on the Certificate of Title for the burdened property and are typically shown on the deposited plan, the survey plan of the property. They are disclosed in the Section 32 vendor statement in Victoria and in the contract of sale in other states. However not all easements are immediately obvious, some are implied by law rather than registered on the title, and some older easements may be described in ways that are not immediately clear to a non-lawyer.

Types of easements and their building implications

Easement typeWhat it allowsWho holds itBuilding implication
Drainage easementDrainage or stormwater pipes to pass through the land, council or utility can access for maintenanceCouncil or water authorityCannot build permanent structures over or within the easement, setback typically 1 metre each side of pipe centreline
Sewerage easementSewer pipes to pass through the land, council or water authority can accessCouncil or water authorityCannot build over, council requires clearance typically 1 metre each side, can affect building position significantly
Services easement, electricity, gas, telecommunicationsUnderground or overhead utility services to pass through or over the landUtility providerCannot build over underground services, height restrictions under overhead lines
Right of way, privateA neighbouring property owner has the right to pass across part of your land, typically for vehicle or pedestrian accessNeighbouring property ownerCannot obstruct the right of way, may not be able to fence or gate without easement holder's consent
Right of way, publicPublic access through part of your land, less common in residentialCouncil or publicCannot obstruct or permanently close the public right of way
Carriageway easementVehicle access across part of your land, typically shared driveway accessBenefiting property ownerShared driveway maintenance obligations, cannot narrow or obstruct
Restriction on useRestricts how the land can be used, height limits, land use restrictions, conservationCouncil, developer or neighbouring ownerMay prevent construction above a certain height or certain land uses
Party wall easementShared wall between two propertiesNeighbouring property ownerRestricts what can be done with the shared wall, demolition or modification requires consent
Easement for light and airPrevents obstructing light or air to a neighbouring propertyNeighbouring property ownerRestricts building height or position to preserve light to the benefiting property

Easement type

Drainage easement

What it allows

Drainage or stormwater pipes to pass through the land, council or utility can access for maintenance

Who holds it

Council or water authority

Building implication

Cannot build permanent structures over or within the easement, setback typically 1 metre each side of pipe centreline

Easement type

Sewerage easement

What it allows

Sewer pipes to pass through the land, council or water authority can access

Who holds it

Council or water authority

Building implication

Cannot build over, council requires clearance typically 1 metre each side, can affect building position significantly

Easement type

Services easement, electricity, gas, telecommunications

What it allows

Underground or overhead utility services to pass through or over the land

Who holds it

Utility provider

Building implication

Cannot build over underground services, height restrictions under overhead lines

Easement type

Right of way, private

What it allows

A neighbouring property owner has the right to pass across part of your land, typically for vehicle or pedestrian access

Who holds it

Neighbouring property owner

Building implication

Cannot obstruct the right of way, may not be able to fence or gate without easement holder's consent

Easement type

Right of way, public

What it allows

Public access through part of your land, less common in residential

Who holds it

Council or public

Building implication

Cannot obstruct or permanently close the public right of way

Easement type

Carriageway easement

What it allows

Vehicle access across part of your land, typically shared driveway access

Who holds it

Benefiting property owner

Building implication

Shared driveway maintenance obligations, cannot narrow or obstruct

Easement type

Restriction on use

What it allows

Restricts how the land can be used, height limits, land use restrictions, conservation

Who holds it

Council, developer or neighbouring owner

Building implication

May prevent construction above a certain height or certain land uses

Easement type

Party wall easement

What it allows

Shared wall between two properties

Who holds it

Neighbouring property owner

Building implication

Restricts what can be done with the shared wall, demolition or modification requires consent

Easement type

Easement for light and air

What it allows

Prevents obstructing light or air to a neighbouring property

Who holds it

Neighbouring property owner

Building implication

Restricts building height or position to preserve light to the benefiting property

How easements affect construction

Easement typeTypical restriction on constructionWhat requires easement holder consentWhat happens if you build without consent
Drainage or sewerage easementNo permanent structures within the easement area, typically 1 metre each side of pipe centrelineAny structure within or over the easementCouncil or water authority can require demolition at owner's cost, no compensation
Services easement, undergroundNo structures over underground servicesAny structure in the easement corridorUtility provider can require removal at owner's cost
Services easement, overheadHeight restrictions under overhead lines, safety exclusion zoneAny structure or vegetation within the exclusion zoneSafety and legal breach, must be removed
Right of wayAccess must remain unobstructed at all timesFencing, gates or any obstruction of the right of wayEasement holder can apply to court to have obstruction removed
Restriction on useLand use or development restricted as specifiedAny development that breaches the restrictionCouncil can refuse building permit, breach is a planning offence
Carriageway easementDriveway width and surface must be maintainedChanges to the shared drivewayEasement holder can require reinstatement

Easement type

Drainage or sewerage easement

Typical restriction on construction

No permanent structures within the easement area, typically 1 metre each side of pipe centreline

What requires easement holder consent

Any structure within or over the easement

What happens if you build without consent

Council or water authority can require demolition at owner's cost, no compensation

Easement type

Services easement, underground

Typical restriction on construction

No structures over underground services

What requires easement holder consent

Any structure in the easement corridor

What happens if you build without consent

Utility provider can require removal at owner's cost

Easement type

Services easement, overhead

Typical restriction on construction

Height restrictions under overhead lines, safety exclusion zone

What requires easement holder consent

Any structure or vegetation within the exclusion zone

What happens if you build without consent

Safety and legal breach, must be removed

Easement type

Right of way

Typical restriction on construction

Access must remain unobstructed at all times

What requires easement holder consent

Fencing, gates or any obstruction of the right of way

What happens if you build without consent

Easement holder can apply to court to have obstruction removed

Easement type

Restriction on use

Typical restriction on construction

Land use or development restricted as specified

What requires easement holder consent

Any development that breaches the restriction

What happens if you build without consent

Council can refuse building permit, breach is a planning offence

Easement type

Carriageway easement

Typical restriction on construction

Driveway width and surface must be maintained

What requires easement holder consent

Changes to the shared driveway

What happens if you build without consent

Easement holder can require reinstatement

How to find easements on a property in Australia

Check the Certificate of Title

The most reliable way to identify registered easements is to obtain a copy of the current Certificate of Title for the property, available through the relevant state land titles office. Easements registered on the title are listed in the encumbrances section of the title. In Victoria, NSW, Queensland and other states, the titles office online portal provides title searches for a small fee, typically $15 to $30.

Check the deposited plan

The deposited plan, the survey plan of the property, typically shows the physical location and dimensions of easements as hatched or shaded areas. The deposited plan number is shown on the Certificate of Title and can be obtained from the same titles office search. The deposited plan shows where the easement sits within the property boundaries, which is essential for understanding the building implications. A site survey provides the on-the-ground data showing easement locations relative to existing features, while a contour survey adds the level information needed for design. A qualified land surveyor prepares both of these and marks all easement locations on the survey plan.

Check the Section 32 or vendor statement

In Victoria, the Section 32 vendor statement must disclose all registered easements. In other states, the contract of sale should disclose known encumbrances. These documents are provided before contract signing, review them carefully with a property lawyer before committing. For off-the-plan purchases, the off-the-plan risks guide and the documents to review before buying off-the-plan guide cover the additional easement disclosure requirements.

Services location, Dial Before You Dig

The Dial Before You Dig service, 1100 or dialbeforeyoudig.com.au, provides information about underground utility services near a planned excavation. This is not a substitute for a title search, underground services may exist that are not registered as formal easements, but it identifies utility infrastructure that may affect construction.

Engage a property lawyer

For any property purchase where easements may affect the intended development, engage a property lawyer to review the title search results and advise on the implications before signing the contract. A lawyer can identify not just registered easements but also implied easements and restrictive covenants that may not be immediately obvious from the title alone. Where the site is sloped, easements may also affect cut and fill earthworks positioning. Engaging an architect early for a pre-purchase assessment ensures the design accounts for easement constraints from the outset.

Easements and development applications

Easements affect development applications in two distinct ways, they affect what can physically be built and where, and they may affect the planning assessment of the proposed development.

Physical building restrictions

The most direct impact of an easement on a development application is the physical restriction on where structures can be placed. A development application that proposes a structure within or over a registered easement will typically be refused by the building certifier, or if approved, the structure will need to be removed when the easement holder exercises their rights. Council and building certifiers check for easements as part of the assessment process, the construction certificate and private certifier vs council approval guides explain how this assessment works, but the applicant bears the responsibility for knowing about and accounting for easements in their design.

Setbacks from easements

Most councils and utility providers require minimum setbacks from easement boundaries for permanent structures, typically 1 metre from each side of a drainage or sewerage pipe centreline. These setbacks are in addition to the normal building setbacks and envelope controls that apply from property boundaries. On a narrow site, an easement running through the middle of the block can effectively prevent development of a significant portion of the site.

Easement modification or extinguishment

It is possible in some circumstances to modify or extinguish an easement, but the process is complex, typically requires the consent of the easement holder and can take significant time and cost. For a drainage easement held by council, the process involves applying to council to relocate the drainage infrastructure, which the developer bears the cost of. For a private easement, modification requires negotiation with and consent of the easement holder, which may involve financial compensation.

Easement due diligence checklist

Use this checklist alongside the broader building a house checklist to confirm all easement-related requirements have been addressed. Where construction adjoins neighbouring properties, a dilapidation report should also be commissioned before works begin.

Before purchasing any property, obtain a copy of the current Certificate of Title and identify all registered easements

Obtain the deposited plan and identify the physical location and dimensions of all easements within the property boundaries

In Victoria, review the Section 32 vendor statement for easement disclosures before signing the contract

Engage a property lawyer to advise on the implications of any easements identified, particularly for development sites

Commission a contour and feature survey after purchase, confirm the surveyor marks all easement locations on the survey plan

Check the Dial Before You Dig service, identify underground utilities near the proposed construction area

Confirm the proposed building footprint does not encroach within any easement area or within the required setback from the easement

Confirm any retaining walls, driveways or paths do not encroach within easement areas

If easement modification or relocation is required, engage the process early and allow significant time, easement modifications can take 6 to 18 months

Confirm the building certifier has reviewed easement locations as part of the construction certificate or building permit assessment

Red flags

Proposed building footprint encroaches within a drainage or sewerage easement area, council or water authority can require demolition at owner's cost
Easements were not disclosed in the contract of sale or Section 32, engage a property lawyer to assess your options if undisclosed easements are discovered after purchase
Easement location is not shown on the architect's or builder's site plan, design has been prepared without accounting for easement restrictions
Building certifier has not been provided with the deposited plan showing easement locations before construction documentation is prepared
Right of way easement exists but access is currently obstructed, existing breach creates potential legal liability for the current owner
Overhead powerline easement exists over the proposed building site, height restrictions may prevent the desired building form
Property vendor is unable to provide clear information about easement locations when asked, may indicate undisclosed encumbrances

BUILTLY and property due diligence

BUILTLY is building a record of completed Australian homes that credits the builder, designers and trades behind each one.

BUILTLY is building a record of completed Australian homes that credits the builder, designers and trades behind each one.

Frequently asked questions

What is an easement on a property in Australia?

An easement is a legal right registered on a property title that gives another party, the easement holder, the right to use part of your land for a specific defined purpose. Common easements include drainage easements allowing council to maintain underground pipes, sewerage easements, services easements for electricity and gas infrastructure and rights of way giving neighbours vehicle or pedestrian access across your land. Easements are attached to the land not to the owner, they transfer with the title when the property is sold. They restrict what can be built within the easement area and cannot be removed simply by purchasing the property.

How do I find easements on a property in Australia?

Obtain a copy of the current Certificate of Title from the relevant state land titles office, easements registered on the title are listed in the encumbrances section. Obtain the deposited plan, the survey plan showing the physical location of easements within the property. In Victoria review the Section 32 vendor statement which must disclose registered easements. Engage a property lawyer to advise on the implications of any easements identified. Check the Dial Before You Dig service for underground utility services near the proposed construction area. A thorough title search takes less than an hour and costs $15 to $30, it is one of the most important due diligence steps before any property purchase.

Can I build over an easement in Australia?

Generally no, permanent structures cannot be built within or over most easements without the easement holder's consent. A council or water authority can require demolition of any structure built over a drainage or sewerage easement at the owner's cost and without compensation. Utility providers can require removal of structures over underground services easements. The only permanent structures typically permitted within easement areas are those specifically approved by the easement holder in writing, and these approvals are rarely granted for structures that would prevent access for maintenance. Design your building to avoid easement areas entirely, do not assume approval will be granted.

Can an easement be removed from a property title in Australia?

Yes, but the process is complex and often expensive. Removing or modifying a registered easement requires either the consent of the easement holder, who may require financial compensation, or a court order. For council drainage easements, the process typically involves relocating the drainage infrastructure at the developer's cost, which requires council approval and engineering works. For private easements, rights of way, private drainage, negotiation with the easement holder is required. The process typically takes 6 to 18 months and can cost $20,000 to $100,000 or more depending on the infrastructure involved. Always factor easement modification costs into the development feasibility before purchasing.

What should I check about easements before buying a property in Australia?

Before purchasing, obtain the Certificate of Title and deposited plan and identify all registered easements and their physical locations within the property. Engage a property lawyer to advise on the implications, particularly if the intended development may be affected. Confirm the proposed building footprint does not encroach within any easement area or within the required setback from it. Check the Dial Before You Dig service for underground utilities. If easement modification or relocation is required for the intended development, get a preliminary assessment of the process, timeline and cost before committing to the purchase price, the cost of easement modification can fundamentally affect development viability.