Issued for construction - IFC - is the status on a set of architectural or engineering drawings that tells the builder these are the documents to build from. It sounds straightforward, and it is one of many stages covered in the BUILTLY complete guide to building a house in Australia. In practice the distinction between IFC drawings and earlier drawing revisions - concept drawings, design development drawings, drawings issued for tender, drawings issued for approval - is one of the most consistently misunderstood aspects of the construction documentation process and a source of significant and entirely avoidable construction errors. A builder who constructs from an earlier drawing revision - or from a set of drawings that has been superseded by a later IFC revision - builds something that does not match the current approved design. The cost of correcting that error is typically far higher than the cost of maintaining disciplined drawing revision control throughout the project.
What does issued for construction mean?
Issued for construction - IFC - is a drawing status that confirms a drawing has been through the complete design, coordination and approval process and is authorised to be used as the basis for physical construction. When a drawing is stamped or marked issued for construction it means the architect and relevant engineers have confirmed that the drawing reflects the current approved design, that it has been coordinated with all other drawings in the set and that the builder can rely on it to construct the relevant element. Distinguish the construction issue from earlier tender documents before work proceeds.
IFC is not the only drawing status - drawings go through multiple status stages during the design and construction process. Understanding what each status means - and which status the builder should be constructing from - is the practical foundation of drawing revision management.
The issued for construction status is what distinguishes a document the builder can build from a document the builder should not build from. This distinction matters every time a drawing is revised - which on a complex custom home may happen dozens of times during the design and construction process.
Drawing status progression
| Drawing status | What it means | Can the builder construct from it? | Typical stage |
|---|---|---|---|
| Preliminary - P | Early design stage drawing - not yet coordinated or approved - for discussion only | No - not for construction | Early design - concept stage |
| For coordination - FC | Drawing issued to other consultants for coordination - not yet approved for construction | No - coordination may change the drawing | Design development stage |
| For approval - FA | Drawing issued for owner review and approval - or for development application lodgement | No - owner or authority review may require changes | DA documentation stage |
| For tender - FT | Drawing issued to builders for pricing - represents the design intent at tender stage | For pricing only - not for construction | Tender stage |
| Issued for construction - IFC | Drawing confirmed as current - coordinated - approved - authorised for construction | Yes - this is the construction drawing | Construction documentation stage |
| Revision to IFC - IFC Rev A, Rev B | An updated version of an IFC drawing incorporating changes made after the original IFC was issued | Yes - but only the latest revision - superseded revisions must be removed from site | During construction when changes occur |
| As built - AB | Drawing updated after construction to reflect what was actually built - including any variations | Record purposes only - not for construction | Post-construction |
Drawing revision control - why it matters
Drawing revision control is the process of managing drawing versions so that everyone working on a project - the builder, the subcontractors, the consultants - is always working from the current revision. On a simple project with few drawings and few changes it is straightforward. On a complex custom home with 40 to 80 drawings across architectural, structural and consultant disciplines it requires deliberate management.
The revision numbering system
Drawing revisions are typically numbered using letters - Rev A, Rev B, Rev C - or numbers - Rev 1, Rev 2, Rev 3 - with each revision representing a documented change from the previous version. The revision history block on each drawing - typically in the title block - records every revision, its date and a brief description of what changed. The current revision is always the highest letter or number in the sequence.
The superseded revision problem
When a new revision is issued - superseding the previous revision - the old revision must be removed from the construction site and replaced with the current revision. A builder who constructs from Rev A when Rev B has been issued is building from a superseded drawing - the element they construct may not match the current approved design. This is one of the most common and most preventable construction errors.
The transmittal record
Every time drawings are issued - whether at IFC, at a subsequent revision or for any other purpose - a transmittal document should be issued recording what drawings were issued, at what revision, to whom and on what date. The transmittal record creates an auditable history of what drawings each party had access to - which is critical in any dispute about whether a builder was constructing from the correct revision.
Drawing revision control
| Revision event | What the architect does | What the builder does | What the homeowner should confirm |
|---|---|---|---|
| Initial IFC issue | Issues complete IFC drawing set with transmittal - all drawings marked IFC | Receives drawing set - confirms receipt on transmittal - distributes to relevant subcontractors | Confirm receipt of transmittal - confirm all drawings are marked IFC |
| Revision to IFC - minor | Issues revised drawing with new revision letter - transmittal identifying changed drawing and revision | Removes superseded revision from site - replaces with current revision - notifies affected subcontractors | Confirm revised drawing has been issued and acknowledged |
| Revision to IFC - significant | Issues revised drawing - may also issue RFI response or variation notice if the revision changes the scope or cost | Reviews revision - identifies any cost or programme impact - submits variation claim if warranted | Confirm the revision is understood and accepted - confirm variation claim if raised |
| As-built update | Issues as-built drawing reflecting what was actually constructed | Provides mark-up of any differences between IFC and as-built to architect | Confirm as-built drawings are prepared and retained |
The complete drawing set - what IFC covers
An IFC drawing set for a custom residential project is not a single drawing - it is a coordinated set of drawings across multiple disciplines that together define every element of the building. Understanding what a complete IFC set contains - and what is missing when a set is incomplete - is the foundation of managing the construction documentation process.
Architectural drawings
The architectural IFC set typically includes a site plan showing the building position, orientation and relationship to boundaries and easements, floor plans for every level showing all room dimensions and spatial relationships, all four elevations showing the external form and materials, sections through the building showing vertical relationships, roof plan showing the roofing geometry and drainage, internal elevations of key spaces - kitchen, bathrooms, joinery walls - and detail drawings showing how specific elements are constructed at a larger scale. For a homeowner unfamiliar with this documentation, our guide on how to read house plans in Australia explains how to interpret the floor plans and elevations. For a standard custom home the architectural IFC set typically comprises 20 to 50 drawings depending on complexity.
Structural drawings
The structural IFC set includes footing and slab drawings showing the footing specification and reinforcement layout, floor framing drawings where applicable, roof framing or truss layout drawings, connection details and any special structural elements. The structural drawings are coordinated with the architectural drawings - the footing dimensions on the structural drawings must match the building position on the architectural site plan.
Consultant drawings
Depending on the project's complexity the IFC set may also include hydraulic drawings for stormwater and drainage design, landscape drawings for external works, electrical drawings for complex electrical systems or smart home infrastructure and mechanical drawings for HVAC where a mechanical engineer has been engaged.
The coordination requirement
The IFC drawing set must be internally coordinated - all drawings must be consistent with each other. A wall that is shown at 3600mm on the floor plan must be shown at 3600mm on the elevation and the section. A structural beam shown at a specific level on the structural drawings must match the ceiling height shown on the architectural sections. Coordination failures - inconsistencies between drawings in the IFC set - are one of the most common sources of construction errors and variation claims.
What happens when the IFC set is incomplete
An incomplete IFC set - where some drawings have been issued for construction while others are still at an earlier status - is one of the most common and most problematic situations in residential construction. It arises when schedule pressure drives the builder to commence construction before all documentation is complete.
The provisional sum consequence
When a portion of the design is not yet documented to IFC standard - typically external works, landscaping, joinery or specialist elements - the builder includes a provisional sum in the contract price for that element. The provisional sum represents an estimate of what the undocumented element will cost when it is eventually designed and documented. Provisional sums frequently exceed their estimates - see the companion guide Provisional Sum vs Prime Cost Item Australia for the full framework.
The variation sequence
When the missing IFC documentation is eventually prepared and issued, the builder reviews it against the provisional sum estimate in the contract. If the documented scope or specification is more expensive than the provisional sum, the builder submits a variation claim for the difference. This is not a builder overcharging - it is the direct consequence of contracting before the documentation was complete.
The programme consequence
Incomplete IFC documentation also affects the construction programme. A builder who is waiting for IFC drawings to proceed with a specific element cannot maintain the planned programme - the missing drawings create a hold point that delays the affected work. See the companion guide Construction Programme Australia for how drawing issue timing should be reflected in the programme.
The most important principle
The building contract should not be signed before the complete IFC drawing set is available - or at minimum, the elements with incomplete documentation should be identified and the provisional sum estimates should be realistic assessments of likely cost, not optimistic figures designed to make the contract price appear lower.
Drawing register - managing the current set on site
A drawing register is the tool that ensures the builder and all subcontractors are always working from the current revision of every drawing. It is a simple document - a table listing every drawing in the IFC set, its current revision letter and the date the current revision was issued - but it is one of the most important documents on any construction site.
What a drawing register contains
For every drawing in the IFC set the register records the drawing number, the drawing title, the discipline - architectural, structural, hydraulic - the current revision letter and the date the current revision was issued. When a new revision is issued the register is updated - the new revision letter and issue date replace the previous entry.
Who maintains it
The drawing register is typically maintained by the builder - the principal contractor - who receives all drawing issues from the architect and consultants and distributes them to the relevant subcontractors. The architect may also maintain a parallel issue record - the transmittal register - that records every drawing issued to the builder with the date and revision.
How to use it
Before any physical work commences on a specific element - frame erection, joinery installation, window installation - confirm that the drawing being used is at the current revision shown in the drawing register. A subcontractor who uses a superseded revision is working from information that may have changed - the discrepancy is discovered when the installed element does not match the current design.
RFI process - clarifying the IFC drawings during construction
Even a well-prepared IFC drawing set will generate questions during construction - conditions encountered on site that differ from what the drawings assumed, elements that need further clarification and coordination issues between trades. The request for information - RFI - process is the formal mechanism for raising and resolving these questions.
What an RFI is
A request for information is a formal written query submitted by the builder to the architect or engineer asking for clarification on a specific aspect of the IFC drawings. The architect responds in writing - the RFI response becomes part of the project record and may result in a drawing revision if the clarification requires the drawing to be updated.
Why the RFI process matters
An RFI that is not formally submitted and responded to in writing creates a verbal instruction - the builder proceeds based on a verbal conversation with the architect that may not be correctly remembered or may not reflect the architect's actual intent. When the completed element does not match the design, the absence of a written RFI record makes it impossible to determine whether the builder was acting on correct instructions.
The timing issue
RFIs submitted too late - after the physical work has been performed - serve no purpose. The RFI process is most valuable before the work is done - when the clarification can inform the construction rather than explain it after the fact. Builders should submit RFIs as soon as they identify a question - not after they have made their own interpretation and proceeded.
As-built drawings - the final record
After construction is complete the IFC drawings are updated to reflect what was actually built - incorporating all changes made during construction through variations, RFI responses and field adjustments. The resulting as-built drawings - also called record drawings - are the permanent record of the completed building.
Why as-built drawings matter
A future owner who needs to renovate, extend or perform structural work on a completed building needs to know what was actually built - not just what was designed. The as-built drawings show the actual dimensions, the actual structural system and the actual location of services - information that cannot be reliably determined from the IFC drawings if changes were made during construction.
Who prepares them
As-built drawings are typically prepared by the architect - who updates the IFC set based on mark-ups provided by the builder. The builder's site team should record all changes from the IFC drawings during construction - variations approved, RFI responses that changed the design, field adjustments - so the architect has the information needed to prepare accurate as-built drawings. See the companion guide As-Built Drawings Australia for the complete framework.
What is commonly missed
Services as-built drawings - showing the actual location of underground drainage, water supply pipes and electrical conduit - are the most practically important and most commonly absent as-built documentation. A future owner who needs to excavate, renovate or extend a building without knowing where the services are located is working blind. Services as-built drawings should be requested as a handover document.
The difference between IFC drawings and tender drawings
One of the most common misunderstandings in residential construction is the assumption that the drawings issued for tender - the drawings the builder priced from - are the same as the IFC drawings the builder constructs from. They should be - but frequently they are not.
When tender drawings become IFC
After a builder is selected from tender, the architect typically reviews the tender drawings, incorporates any changes arising from the tender process - RFI responses, value engineering, design revisions requested by the owner - and issues the updated set as the IFC set. The IFC set is then attached to the building contract as the contract drawings.
When they differ
If the design was not complete at tender - which is common when tendering is accelerated - the tender drawings may be at design development stage rather than construction documentation stage. The IFC drawings - prepared after the contract is signed - may differ significantly from the tender drawings in specification, detail and dimension. This is one of the primary sources of variation claims - the builder tendered against incomplete drawings and the IFC drawings show a more detailed or more expensive design than the builder priced.
The most important principle
The building contract should clearly identify which drawing set - with revision numbers - forms the contract documents. The IFC drawing set - not the tender drawings, not the DA drawings, not the concept drawings - should be the contract drawing set. Any drawing not in the IFC set at the time of contract signing is not a contract document.
IFC drawing review checklist
IFC drawing review checklist
- Before construction commences - confirm the complete IFC drawing set has been received - confirm all drawings are marked issued for construction with the current revision letter
- Confirm the IFC drawing set is attached to and referenced in the building contract - these are the contract drawings
- Confirm the builder has signed the transmittal acknowledging receipt of the IFC drawing set
- Confirm all previous drawing revisions have been removed from the construction site and replaced with the IFC set
- When a drawing revision is issued during construction - confirm the builder acknowledges receipt by signing the transmittal
- When a drawing revision is issued - confirm the superseded revision is removed from the site and any affected subcontractors are notified
- Confirm the builder maintains a current drawing register on site - showing the current revision of every drawing
- If a variation claim is submitted arising from a drawing revision - review the revision against the tender drawings to confirm whether the revision represents a genuine change to the scope priced at tender
- At practical completion - confirm as-built drawings are prepared reflecting any differences between the IFC set and what was actually constructed
- Retain the complete IFC drawing set and all revision transmittals permanently - these are essential records for any future renovation or structural work
Red flags
Red flags in IFC drawing management
- ✕Builder cannot confirm which drawing revision they are constructing from when asked - drawing revision control is not being managed
- ✕Superseded drawings are present on the construction site alongside current revisions - builder may be constructing from the wrong revision
- ✕No transmittal records exist confirming which drawings were issued and when - no auditable drawing issue history
- ✕Builder received the tender drawings but no IFC set was issued before construction commenced - builder is constructing from tender drawings that may not be the current approved design
- ✕The building contract does not identify the drawing set by revision number - the contract drawings are not clearly defined
- ✕Architect is issuing drawing revisions without transmittals - no record of what was issued and when
- ✕Builder proceeds with work that is affected by a drawing revision without acknowledging the revision - work may be based on the superseded drawing
BUILTLY and lasting project records
BUILTLY and lasting project records
The IFC drawing set - the drawings the building was actually constructed from - is the most important technical document in any completed building's record. A future owner, renovator or structural engineer who can access the original IFC drawings for a completed building has independently verifiable information about what was designed and approved that cannot be reconstructed without the original documentation.
BUILTLY is building a record of completed Australian homes that credits the builder, designers and trades behind each one.
Frequently asked questions
What does issued for construction mean in Australia?
Issued for construction - IFC - is a drawing status that confirms a drawing has been through the complete design, coordination and approval process and is authorised as the basis for physical construction. When a drawing is marked IFC it means the architect and engineers have confirmed it reflects the current approved design, it has been coordinated with all other drawings in the set and the builder can rely on it to construct the relevant element. IFC drawings are the contract drawings - the documents attached to the building contract that define what the builder is legally obligated to construct.
What is the difference between IFC drawings and tender drawings?
Tender drawings are issued to builders for pricing - they represent the design at the time of tender and form the basis for the builder's price. IFC drawings are issued after the builder is selected and the contract is negotiated - they represent the current approved design that the builder will actually construct. Tender drawings and IFC drawings should be the same if the design was complete at tender. They frequently differ if the design was not fully resolved at tender - which is common when tendering is accelerated. Any difference between the tender drawings and the IFC drawings may generate variation claims.
What is drawing revision control and why does it matter?
Drawing revision control is the process of managing drawing versions so that everyone working on a project is always working from the current revision. Each time a drawing is updated a new revision letter or number is issued - Rev A, Rev B, Rev C - and the superseded revision must be removed from the construction site and replaced with the current version. A builder who constructs from a superseded revision builds something that does not match the current approved design - a construction error that may require demolition and reconstruction to correct. Disciplined revision control - maintained through transmittal records and a current drawing register on site - prevents this category of entirely avoidable construction error.
Can a builder construct from drawings that are not marked issued for construction?
No - a builder should only construct physical elements from drawings marked issued for construction. Drawings at earlier status stages - preliminary, for coordination, for approval, for tender - may not reflect the final approved design and may be superseded by the time construction commences. If a builder constructs from a non-IFC drawing and the element does not match the IFC design, the cost of rectification is typically the builder's responsibility - they constructed from a document they were not authorised to build from.
What should I do if I discover my builder is using superseded drawings?
Notify the builder in writing immediately - identify the specific drawing, the superseded revision the builder is using and the current IFC revision that should be used. If physical work has already been constructed from the superseded drawing, engage the architect to assess whether the constructed element matches the current IFC design - and whether rectification is required. Document the discovery with dated photographs and retain all correspondence. The cost of rectifying work constructed from a superseded drawing is typically the builder's responsibility - they are obligated to construct from the current IFC drawings.