When a homeowner or developer invites builders to price their project, the quality of the tender documents - the package of drawings, specifications and information provided to each builder - directly determines the quality of the tenders received. A builder who receives a complete, well-coordinated tender set with architectural drawings, structural drawings, a detailed specification and a schedule of finishes can produce a detailed, accurate and comparable tender price. A builder who receives a concept design and a vague description of the project produces a price full of assumptions, allowances and provisional sums that bears little resemblance to the actual project cost. Understanding what a complete tender document set contains, what each document does and what the consequences are when the tender set is incomplete is essential knowledge for any homeowner or developer approaching the tendering stage of a construction project.
What are tender documents?
Tender documents are the complete package of information provided to builders when they are invited to submit a price for a construction project. They form the basis on which builders prepare their tender - the price and programme they submit for the work. After a builder is selected and a contract is negotiated, the tender documents - or a version of them - typically become the contract documents, forming part of the legally binding agreement between the owner and the builder.
The quality and completeness of the tender documents determines the accuracy of the tender prices received, the comparability of prices between different builders, the number and value of variations during construction and the extent to which the contract price reflects the final cost of the project.
A complete tender document set for a residential construction project typically includes architectural drawings, structural drawings, a specification, a schedule of finishes, a schedule of fittings and fixtures, a site survey and geotechnical report and any other consultant documentation relevant to the project. Each document serves a distinct purpose - and the absence of any one of them creates gaps that builders fill with assumptions.
Tender document set by document type
| Document | What it contains | Who prepares it | What happens without it |
|---|---|---|---|
| Architectural drawings - construction documentation | Floor plans, elevations, sections, details - all dimensions and spatial relationships confirmed | Architect | Builder prices from incomplete or concept drawings - assumptions create variations |
| Structural drawings | Footing specification, frame design, connection details, structural notes | Structural engineer | Builder includes a provisional sum for structural work - significant variation risk |
| Specification | Written description of all materials, finishes, products and workmanship standards | Architect - sometimes quantity surveyor | Builder prices to their own standard - not the owner's specification - quality disputes arise |
| Schedule of finishes | Room by room listing of all floor, wall and ceiling finishes - tile types, paint colours, carpet grades | Architect or interior designer | Builder uses provisional sums or standard finishes - not the owner's selections |
| Schedule of fittings and fixtures | Listing of all specified tapware, light fittings, appliances, door hardware, sanitary fittings | Architect or interior designer | Builder uses provisional cost allowances - actual selections may exceed allowances significantly |
| Site survey - contour and feature | Existing ground levels, boundaries, features, easements | Land surveyor | Builder cannot accurately price earthworks and site preparation |
| Geotechnical report | Soil classification, bearing capacity, groundwater conditions | Geotechnical engineer | Builder uses a provisional sum for footings - significant variation risk if soil conditions are worse than assumed |
| Existing conditions drawings - alterations and additions | Record of existing building conditions for renovation projects | Architect - from measured survey | Builder cannot accurately price interface between new and existing work |
| Hydraulic drawings | Stormwater, drainage and water supply design | Hydraulic engineer - for complex sites | Builder prices drainage on assumptions - may not meet council or authority requirements |
| Landscape drawings | Landscaping scope, species, levels, irrigation | Landscape architect | Landscaping excluded from or inadequately covered in the tender |
| Form of tender | Standard document specifying what the builder must price and submit | Architect or quantity surveyor | Inconsistent tender submissions - difficult to compare |
What each tender document does
The architectural drawings - the foundation of the tender
The architectural construction documentation drawings are the most important component of the tender set. They define every spatial, dimensional and material aspect of the project - the floor plan confirms what is being built and where, the elevations confirm the external form, the sections confirm the vertical relationships and the details confirm how specific elements are constructed.
Architectural drawings prepared to construction documentation standard - not concept or design development standard - contain sufficient detail for an experienced builder to price the work accurately. Drawings at concept stage contain insufficient detail - the builder must make assumptions about element specifications, interface conditions and construction method that introduce uncertainty into the tender price. Understanding the pre-construction stage helps clarify when these drawings should be completed.
The structural drawings - determining the footing and frame cost
The structural drawings define the footing specification - which directly determines the most variable cost element in any residential construction project. A footing designed for a Class M site in a reactive soil area costs significantly more than a footing designed for a Class A stable site. Without structural drawings, the builder includes a provisional sum based on their assumption of the likely footing requirement - which may be significantly lower than the actual specification. For more detail on the structural engineering role, see our guide to structural engineers in Australia.
The specification - defining quality
The specification is the written companion to the drawings - it describes the quality, performance and installation requirements for every material, product and system in the project. Where the drawings show what and where, the specification describes to what standard. A project tendered without a specification produces tenders priced to the builder's standard - which may be significantly different from the owner's expectations.
The schedules - defining the selections
The schedules of finishes, fittings and fixtures translate the owner's selections into a format builders can price. Without confirmed selections, builders price to provisional cost allowances - budget estimates that are frequently exceeded when the owner makes their actual selections. Converting provisional cost allowances to confirmed lump sum selections before tender is the single most effective way to reduce variation risk. For more on how shop drawings translate selections into fabrication documents, see the companion guide.
Complete vs incomplete tender set
| Factor | Complete tender set | Incomplete tender set |
|---|---|---|
| Tender price accuracy | High - builder prices to confirmed specifications and dimensions | Low - builder prices to assumptions - provisional sums throughout |
| Price comparability between builders | High - all builders pricing the same scope to the same specifications | Low - each builder makes different assumptions - prices are not comparable |
| Variation risk during construction | Low - scope is clearly defined - few gaps for variation claims | High - every assumption the builder made at tender becomes a potential variation |
| Provisional sum proportion of contract | Low - typically under 5 percent of contract value | High - may be 20 to 40 percent of contract value - final cost highly uncertain |
| Post-contract disputes | Low - contract documents clearly define what was agreed | High - disputes about scope, specification and quality are common |
| Final project cost vs tender price | Close - typically within 5 to 10 percent | Often significantly higher - 20 to 40 percent over tender price is common |
| Builder's confidence in their price | High - limited exposure to unknown conditions | Low - builder prices conservatively or includes large contingencies |
| Time to prepare tender | Longer - more information to review | Shorter - but produces a less reliable price |
The tendering process - how it works
Selecting builders to tender
The architect typically recommends a shortlist of builders - typically two to four - who have demonstrated capability to deliver projects of the relevant type, scale and specification. Inviting too many builders to tender produces a large volume of tender submissions to review without improving the quality of the result. Inviting one builder produces a price without competitive tension. Two to four builders from a qualified shortlist is the standard practice for custom residential projects. For guidance on selecting builders, see how to choose a builder.
The tender period
Builders need adequate time to review the tender documents, seek clarifications, obtain subcontractor prices and prepare their submissions. For a standard custom home a tender period of four to six weeks is typical. Shorter tender periods produce less accurate prices - builders submit contingency-heavy prices when they have not had adequate time to price thoroughly.
Requests for information - RFIs
During the tender period builders typically submit requests for information - RFIs - asking the architect to clarify ambiguities or provide additional information. The architect's responses to RFIs are issued to all tendering builders simultaneously - maintaining the integrity of the competitive process. The number and nature of RFIs received during the tender period is a useful indicator of how complete the tender documents are - a large volume of RFIs indicates gaps in the documentation.
Tender evaluation
After tenders are received the architect prepares a tender analysis - a side-by-side comparison of each builder's price broken down by trade or element, showing where prices differ significantly and identifying any inclusions or exclusions that affect comparability. The tender analysis is presented to the owner with a recommendation. The cheapest tender is not necessarily the best - a significantly lower price typically reflects either more risk carried by the builder - which becomes variations - or scope excluded from the price.
What incomplete tender documents cost
The financial consequences of tendering with incomplete documents manifest primarily as variations during construction - additional cost claims from the builder for work that was not included in the tender price because the information was not available at tender.
The maths
A $1,200,000 custom home tendered without structural drawings - with a $45,000 provisional sum for footings - that is actually founded on a Class H reactive site requiring a $85,000 engineered footing system generates a $40,000 variation on the first day of construction.
The same project tendered without confirmed joinery selections - with $80,000 in PC items for kitchen and joinery - where the owner selects $115,000 worth of joinery generates a $35,000 variation at the joinery ordering stage.
These two variations alone add $75,000 to a project tendered at $1,200,000 - a 6.25 percent increase that could have been substantially avoided through complete tender documentation.
The programme consequence
Incomplete tender documentation also affects the programme - variations arising from incomplete documentation require design decisions, subcontractor pricing and approval processes that were not in the original construction timeline. Each variation adds time as well as cost. Understanding the construction stage helps clarify where these delays typically occur.
Tender document review checklist
Tender document review checklist
- Confirm architectural drawings are at construction documentation standard - not concept or design development - before issuing for tender
- Confirm structural drawings are included in the tender set - not deferred to a post-contract provisional sum
- Confirm a written specification is included - describing workmanship and material standards for all major elements
- Confirm schedules of finishes, fittings and fixtures are included - with confirmed selections converting PC items to lump sum prices wherever possible
- Confirm the site survey is included - contour and feature survey at the current issued for construction standard
- Confirm the geotechnical report is included - soil classification confirmed and footing specification in the structural drawings
- Confirm all specialist consultant drawings are included - hydraulic, landscape - where applicable
- Confirm a form of tender is issued to all builders - specifying what must be included and excluded and the format of the submission
- After receiving tenders - count the number of provisional sums in each tender - a high proportion of provisional sums indicates the tender set was not complete enough for accurate pricing
- After receiving tenders - compare the provisional sum allowances between builders - significant variation in allowances for the same item indicates insufficient information was provided
Red flags
Red flags in the tendering process
- ✕Builder is invited to tender before structural drawings are complete - footing specification is a provisional sum in every tender
- ✕Tender period is less than three weeks for a custom home - insufficient time for accurate pricing
- ✕Tender set does not include a written specification - builders will price to their own standard
- ✕A large proportion of the tender price is provisional sums and PC items - the final project cost is highly uncertain
- ✕All three tenders received are within 2 percent of each other - may indicate builders have priced conservatively to the same assumptions rather than genuinely competitive pricing
- ✕One tender is significantly lower than the others - the low tenderer has either excluded scope or is carrying significant risk that will become variations
- ✕Builder requests a large number of RFIs during the tender period - tender documents are incomplete or unclear
- ✕Architect recommends proceeding without a tender process - engaging a builder at cost plus without competitive tension removes the primary cost control mechanism
BUILTLY and lasting project records
BUILTLY and lasting project records
The tender documents - and the contract documents they become - are the foundation of the technical record for any completed construction project. For future owners, renovators or developers working on a completed building, access to the original tender and contract documentation provides a level of project knowledge - the specified materials, the structural system, the approved drawings - that is otherwise only recoverable through new investigation.
BUILTLY is building a record of completed Australian homes that credits the builder, designers and trades behind each one.
Frequently Asked Questions
What are tender documents in construction in Australia?
Tender documents are the complete package of information provided to builders when they are invited to submit a price for a construction project. A complete residential tender set includes architectural construction drawings, structural drawings, a written specification, a schedule of finishes, a schedule of fittings and fixtures, a site survey and a geotechnical report. The quality and completeness of the tender documents directly determines the accuracy of the tenders received, the comparability of prices between builders and the number of variations during construction. Incomplete tender documents produce unreliable tender prices and high variation risk.
What should be included in a residential construction tender document set?
A complete residential construction tender set should include architectural drawings at construction documentation standard - not concept - structural drawings with confirmed footing specification, a written specification describing workmanship and material standards, a schedule of finishes confirming floor, wall and ceiling selections, a schedule of fittings and fixtures confirming tapware, appliances and hardware, a contour and feature site survey and a geotechnical investigation report. For complex sites - hydraulic drawings and landscape drawings should also be included. The more complete the tender set the more accurate and comparable the tenders received will be.
What is the difference between tender documents and contract documents?
Tender documents are the information provided to builders before they submit their price - they form the basis for the tender. Contract documents are the documents that form the legally binding building contract after a builder is selected and a contract is signed. In most residential projects the tender documents - or a revised and updated version of them - become the contract documents. The contract documents define what the builder is legally obligated to deliver - so their completeness and accuracy directly affects the owner's rights if disputes arise about scope, specification or quality.
What happens if the tender documents are incomplete?
Incomplete tender documents produce tender prices full of provisional sums and prime cost allowances - estimates that may differ significantly from the actual cost when the relevant items are defined. Each provisional sum or PC item that exceeds its tender estimate becomes a variation - additional cost that was not in the original contract price. A project tendered without structural drawings and confirmed finishes selections can easily generate $50,000 to $150,000 in variations on a $1,200,000 project - entirely predictable and largely avoidable through complete tender documentation. Incomplete tender documents also make it difficult to compare tenders between builders because each builder has priced different assumptions.
How long should the tender period be for a residential construction project in Australia?
For a standard custom home a tender period of four to six weeks is typical - sufficient time for builders to review the tender documents thoroughly, seek clarifications through the RFI process, obtain subcontractor prices and prepare detailed submissions. Shorter tender periods of two to three weeks produce less accurate prices - builders include larger contingencies when they have not had adequate time to price thoroughly. For large or complex projects - above $2,000,000 or with significant specialist elements - a tender period of six to eight weeks is appropriate. The tender period should be specified in the tender invitation and should not be shortened to accelerate the programme - the cost of an inadequate tender period is typically much higher than the time saved.