What is a provisional sum?
A provisional sum - PS - is an estimated allowance included in a building contract for an item of work whose scope or cost cannot be determined precisely at the time of contracting. The builder includes a preliminary estimate - the provisional sum - and the contract price is adjusted up or down when the actual cost of that item is determined during construction.
Common examples of provisional sums in residential building contracts include earthworks and site preparation - where the actual cost depends on soil conditions and rock encountered during excavation - demolition on existing sites - where the extent of demolition cannot be fully determined until work commences - external works and landscaping - where the scope is not yet designed - and connection to services - where the authority's requirements are not yet confirmed.
The provisional sum is a budget estimate - not a fixed price. The homeowner's financial exposure is that the actual cost may exceed the provisional sum - sometimes significantly. A provisional sum of $25,000 for earthworks on a sloped site may become $65,000 when rock is encountered during excavation. The difference - $40,000 - is added to the contract price as a variation.
What is a prime cost item?
A prime cost item - PC item - is an allowance included in a building contract for a specific material or product whose selection has not been made at the time of contracting. The builder includes a PC allowance - an estimate of what the item will cost - and the contract price is adjusted when the homeowner makes their selection.
Common PC items in residential building contracts include tapware, light fittings, floor tiles, door hardware, kitchen appliances, bathroom accessories and any other fixture or fitting that the homeowner has not yet selected at the time of signing.
The PC item is also a budget estimate - not a fixed price. The homeowner's financial exposure is that their selected product costs more than the PC allowance. A PC allowance of $3,500 for a tapware set where the homeowner selects a tapware set costing $6,200 generates a $2,700 variation. Across a full house with twelve PC items, these overruns can accumulate to $20,000 to $50,000 above the contract price.
Provisional sum vs prime cost item comparison
| Factor | Provisional sum - PS | Prime cost item - PC |
|---|---|---|
| What it covers | An item of work whose scope or cost is uncertain at contract signing | A specific product or material not yet selected at contract signing |
| Why it is included | Scope or cost cannot be determined - earthworks, demolition, connection to services | Product selection not made - tapware, tiles, appliances, light fittings |
| How the final cost is determined | Actual cost of the work once performed - adjusted up or down from the estimate | Actual cost of the selected product - adjusted up or down from the allowance |
| Who determines the final cost | The builder - based on actual site conditions and work performed | The homeowner - based on their product selection |
| Can it be converted to a lump sum | Yes - once the scope is determined and a fixed price is obtained | Yes - once the homeowner makes their selection before contract signing |
| Typical variation direction | Often over the estimate - actual conditions frequently exceed assumptions | Often over the allowance - homeowners frequently select products above the PC level |
| Contract price impact | Adjusted by variation at the time the actual cost is determined | Adjusted by variation when the selection is confirmed and product is ordered |
| Owner's control over the outcome | Limited - scope is determined by site conditions | Full - owner controls their selections |
Common provisional sums and PC items in residential contracts
| Item | Type | Typical allowance range | Typical actual cost range | Variation risk |
|---|---|---|---|---|
| Earthworks and site preparation | Provisional sum | $15,000 to $40,000 | $15,000 to $150,000+ depending on conditions | High - rock, contaminated soil or uncontrolled fill can significantly exceed estimates |
| Demolition | Provisional sum | $10,000 to $25,000 | $10,000 to $60,000 | Moderate - extent of demolition and hazardous materials affect cost |
| Connection to services - power, water, sewer | Provisional sum | $5,000 to $15,000 | $5,000 to $40,000 | Moderate - authority requirements and distance to connection points vary |
| Landscaping and external works | Provisional sum | $20,000 to $50,000 | $20,000 to $150,000+ | High - scope often not designed at contract signing |
| Kitchen tapware | Prime cost item | $1,500 to $3,500 | $1,500 to $8,000+ | Moderate - homeowners frequently select above the PC allowance |
| Bathroom tapware | Prime cost item - per bathroom | $800 to $2,000 | $800 to $5,000+ | Moderate - per bathroom - multiplied by number of bathrooms |
| Floor tiles - bathroom and wet areas | Prime cost item | $50 to $80 per m² | $50 to $300+ per m² | High - tile selection widely variable |
| Light fittings | Prime cost item | $3,000 to $6,000 | $3,000 to $20,000+ | High - lighting selections vary enormously |
| Kitchen appliances | Prime cost item | $5,000 to $10,000 | $5,000 to $30,000+ | High - appliance selections widely variable |
| Door hardware | Prime cost item | $1,500 to $3,000 | $1,500 to $8,000 | Moderate - specification varies significantly |
Why builders include provisional sums and PC items
Builders include provisional sums and PC items in building contracts for two distinct reasons - one legitimate and one less so.
Legitimate reason - genuine uncertainty
Some items genuinely cannot be fixed priced at the time of contracting. The earthworks cost on a sloped site cannot be precisely determined without a geotechnical investigation confirming what is below the surface. The connection to services cost cannot be fixed priced until the utility authority confirms their requirements. In these cases a provisional sum is the appropriate mechanism - it is an honest acknowledgement that the cost is uncertain.
Less legitimate reason - making the price look lower
A provisional sum or PC item can also be used to make the contract price appear lower than the realistic total project cost. A builder who includes a $20,000 PC allowance for kitchen appliances when the standard specification would cost $35,000 is presenting an artificially low contract price. A builder who includes a $15,000 provisional sum for earthworks on a site they know is likely to require $40,000 of earthworks is presenting an artificially low contract price. The difference emerges as variations - after the contract is signed.
The most effective protection against this practice is to understand the realistic cost of each provisional sum and PC item before signing - not to accept the builder's estimate without question.
Reducing PS and PC risk checklist
Before signing the building contract - list every provisional sum and PC item and understand what the estimate is based on
Commission a geotechnical investigation before signing - to replace the earthworks provisional sum with a lump sum based on known soil conditions
Confirm the demolition scope before signing - to replace the demolition provisional sum with a lump sum based on a demolition contractor's quote
Contact the relevant utility authorities before signing - to confirm service connection requirements and replace those provisional sums with confirmed costs
Make all product selections before signing wherever possible - converting PC items to specified lump sum prices reduces variation risk significantly
For PC items where selection is not yet possible - research the likely cost of your selection range and compare to the builder's PC allowance - if the allowance is below your expected selection range negotiate a higher allowance before signing
Confirm with a quantity surveyor that the provisional sum estimates are realistic for the site conditions and project type
Request that the builder justify each provisional sum estimate - a builder who cannot explain how their estimate was derived may be using unrealistically low figures
Set a budget contingency of at least 10 to 15 percent of the total provisional sums and PC items in your contract - these will almost always exceed the estimates in aggregate
After the contract is signed - make all remaining product selections as early as possible to convert PC items to confirmed costs before they generate variations
Red flags
BUILTLY and lasting project records
BUILTLY and lasting project records
BUILTLY is building a record of completed Australian homes that credits the builder, designers and trades behind each one.
Frequently Asked Questions
What is a provisional sum in a building contract in Australia?
A provisional sum is an estimated allowance included in a building contract for an item of work whose scope or cost cannot be determined precisely at contract signing. Common examples include earthworks - where the actual cost depends on soil conditions - demolition, connection to services and external works. The contract price is adjusted up or down when the actual cost is determined. Provisional sums frequently exceed their estimates - particularly earthworks on sites where the soil conditions are more challenging than the estimate assumed.
What is a prime cost item in a building contract in Australia?
A prime cost item is an allowance included in a building contract for a specific material or product whose selection has not been made at contract signing. Common examples include tapware, tiles, light fittings, appliances and door hardware. The contract price is adjusted when the homeowner makes their selection - up if the selected product costs more than the PC allowance, down if it costs less. PC allowances are frequently exceeded because homeowners select products above the allowance level.
What is the difference between a provisional sum and a prime cost item?
A provisional sum covers an item of work with uncertain scope or cost - the final cost is determined by what actually happens on site, such as the soil conditions encountered during excavation. A prime cost item covers a specific product not yet selected - the final cost is determined by the homeowner's selection. The owner controls the outcome of a PC item through their selection. The owner has limited control over a provisional sum - which is determined by site conditions or authority requirements beyond their direct control.
How do I reduce the number of provisional sums in my building contract?
Commission a geotechnical investigation before signing to replace the earthworks provisional sum with a lump sum. Contact utility authorities before signing to confirm service connection requirements. Obtain demolition quotes before signing. The more pre-contract investigations you complete the more provisional sums can be converted to fixed prices. A quantity surveyor can advise on which provisional sums are genuinely uncertain and which could be fixed priced with additional investigation.
Should I be concerned if my building contract has many PC items?
Yes - a contract with many PC items has a higher final cost uncertainty than one with confirmed lump sum selections throughout. Make all product selections before signing wherever possible - converting PC items to specified lump sum prices. For PC items where you cannot make selections before signing, research the realistic cost of your selection range and compare to the builder's PC allowance - if the allowance is below your expected selection, negotiate a higher allowance before signing. Set a budget contingency of at least 10 to 15 percent of total PC items - they will almost always exceed the allowances in aggregate.
Related guides
What Is a Building Contract in Australia
Variation Claims Construction Australia
Tender Documents Construction Australia
Building Specification Australia
What Is a Progress Claim in Construction Australia
Construction Timeline Breakdown From Design to Handover
Pre-Construction Stage Explained Australia
How to Choose a Builder for Your Home Australia
Builder Complaints and Disputes Australia
Latent Conditions Construction Australia
Site Survey Australia
Soil Testing and Classification Australia