A structural engineer's involvement in a residential construction project does not end when the drawings are submitted for the building permit. The structural engineer has a critical role to play before construction commences and at defined inspection stages during construction - reviewing documentation, assessing site conditions, certifying stage completion and responding to queries that arise as the builder translates drawings into built reality. Most homeowners understand that a structural engineer produces drawings. Far fewer understand what the engineer should be checking before and during construction - and what it means if they are not. This guide covers exactly what a structural engineer should check before construction starts, what mandatory inspections they conduct during construction and what to ask if you are not sure your engineer is doing everything required.

The structural engineer's role before and during construction

The structural engineer's involvement in a residential construction project spans two distinct phases - the design phase and the construction phase. Most homeowners are aware of the design phase - the engineer produces structural drawings that form part of the building permit application. The construction phase involvement is less well understood but equally important.

Design phase - the structural engineer produces the structural drawings and specification from the architectural drawings and geotechnical investigation report. This is the work that most homeowners see - the set of structural drawings submitted with the building permit application.

Construction phase - the structural engineer reviews construction documentation submitted by the builder, conducts mandatory stage inspections, responds to RFIs from the builder, approves any structural variations and certifies stage completion at defined inspection hold points. This is the work that directly protects the homeowner's interests during construction - and the work that is most commonly underdelivered.

The distinction matters because a structural engineer who does design only - producing drawings and then disengaging - provides no assurance that the building is constructed to match those drawings. The construction-phase checks are the mechanism by which the structural engineering design is verified in the actual building. See the companion guide Structural Engineers Australia: What They Do and When to Hire for the full overview of when and why structural engineers are engaged.

What the structural engineer reviews before construction commences

Before the first sod is turned or the first concrete is poured, the structural engineer should have completed a series of documentation reviews that confirm the project is ready to proceed safely.

Review of the geotechnical investigation report

The structural engineer's footing design is based on the soil classification determined by the geotechnical investigation. Before construction commences, the engineer should confirm:

  • The geotechnical report covers the full building footprint - not just a portion of the site
  • The soil classification is consistent across the site - or that variable conditions are identified and addressed in the footing design
  • Any additional site conditions noted in the report - groundwater, acid sulfate soils, fill material, tree root influence - are addressed in the structural design
  • The footing design matches the classification - an H2 site has H2 footing specification, not an assumed M classification

If the geotechnical report raises conditions that were not anticipated in the original structural design, the engineer should revise the footing design before construction commences - not after the slab is poured. See our guides on Soil Testing and Classification Australia and Soil Classification Australia for the complete explanation of soil classifications and their impact on footing design.

Coordination with architectural documentation

The structural drawings must be coordinated with the architectural drawings before construction commences. Contradictions between the two sets of drawings are construction problems that must be resolved before the builder encounters them on site. The structural engineer should confirm:

  • All structural elements are shown on the architectural drawings in their correct locations
  • Ceiling heights accommodate the structural beams and connections shown on the structural drawings
  • The building footprint on the architectural drawings matches the footing layout on the structural drawings
  • Any structural elements that affect the architect's design intent - exposed beams, structural columns, transfer structures - have been resolved with the architect before documentation is finalised

Review of the building permit documentation

The building permit is issued against a specific set of documents. Before construction commences, the engineer should confirm:

  • The structural drawings incorporated into the building permit are the current version - not a superseded set
  • Any conditions on the building permit that relate to structural elements are understood and addressed
  • The building surveyor or certifier has confirmed that the structural documentation meets their requirements

Pre-construction site visit

For projects on complex sites - sloped, reactive clay, coastal, constrained access - a pre-construction site visit by the structural engineer is strongly recommended. The site visit allows the engineer to:

  • Confirm the site conditions match the geotechnical report description
  • Identify any conditions not captured in the investigation - existing structures adjacent to the building footprint, tree root systems near proposed footings, drainage patterns that affect subfloor conditions
  • Confirm construction access for the footing stage - machinery access, proximity to boundaries, any constraints that affect how the slab can be poured

Structural engineer pre-construction checklist

CheckWhat the engineer confirmsWhen it should be complete
Geotechnical report reviewSoil classification covers full footprint, variable conditions addressed, footing design matches classificationBefore structural drawings are finalised
Documentation coordinationStructural and architectural drawings are coordinated - no contradictionsBefore building permit application
Building permit confirmationStructural drawings in permit are current version, permit conditions addressedBefore construction commences
Pre-construction site visitSite conditions match geotechnical report, access confirmed, no unexpected conditionsBefore slab commencement - particularly important for complex sites
Subcontractor confirmationBuilder has confirmed the concreters and framers understand the structural specificationBefore slab commencement
Hold point schedule confirmationBuilder understands which stages require structural inspection before proceedingBefore construction commences
RFI process confirmationBuilder knows the engineer's contact details and response process for construction queriesBefore construction commences

Mandatory stage inspections during construction

The structural engineer's pre-construction checks are followed by mandatory stage inspections at defined points during construction. Where these inspections are hold points, work should not proceed until the inspection is passed; confirm the required stages and who inspects with your building surveyor or certifier. See our guide on Building Inspections Australia for the full inspection framework. For the complete construction stage sequence and what to check at each stage, see our guide to what happens at each stage of building a home in Australia.

StateSlab or base stageFrame stageOther structural inspectionsWho certifies
QueenslandRequired at prescribed stages, including before concrete is pouredRequired - confirm timing with the building certifierRetaining walls, pool shell, any complex structural elementsBuilding certifier - structural engineer provides certification to certifier
New South WalesRequired before pouring reinforced concrete; footing inspections also applyRequired before framework is coveredComplex structural elements as specified in the construction certificate conditionsPrivate certifier - structural engineer provides certification
VictoriaMandatory - building surveyor inspects before frame commencesMandatory - building surveyor inspects before lock-upAs specified in building permit conditionsPrivate or municipal building surveyor - structural engineer provides certification
Western AustraliaNot generally mandatory for ordinary houses - check permit conditionsNot generally mandatory for ordinary houses - check permit conditionsAs specified in building permitPrivate or local government building surveyor
South AustraliaCouncil inspects under its inspection policy - not every houseCouncil inspects under its inspection policy - not every houseAs specifiedPrivate certifier or council

What the structural engineer does at a slab inspection:

  • Excavation depth and footing dimensions match the structural drawings
  • Reinforcement bar size, spacing and placement match the structural specification
  • Reinforcement cover - the distance between the rebar and the concrete surface - meets the specification
  • Any thickened edge beams, pad footings or pier locations are correctly positioned and dimensioned
  • The ground preparation and compaction meet the specification requirements
  • Any waffle pod layout matches the structural drawings
  • All hold-down and connection hardware is correctly positioned before concrete is poured

The slab inspection is a critical hold point - once the concrete is poured, the reinforcement is permanently concealed. Errors discovered after the pour require coring, cutting or in severe cases, demolition and reconstruction.

What the structural engineer does at a frame inspection:

  • Structural member sizes match the structural drawings - correct timber species and grades, correct steel sections
  • Connections between members are correct - nail patterns, bolt sizes, connection hardware
  • Bracing is correctly installed - type, spacing and fixing pattern match the specification
  • Hold-down hardware connecting the frame to the slab is correctly installed
  • Any structural steel elements - beams, columns, portals - are correctly installed and connected
  • Roof framing connections match the structural specification - particularly important in cyclone zones where roof-to-wall connections are engineered components

The frame inspection is the last opportunity to identify and rectify structural errors before the frame is concealed by external cladding and internal linings. For more on the documentation your builder should provide at each stage, see Documents Your Builder Must Provide at Each Stage Australia.

RFIs - requests for information during construction

Between hold point inspections, the structural engineer manages RFIs - requests for information - from the builder. RFIs arise when the builder encounters a situation on site that is not fully addressed by the structural drawings or where a discrepancy, substitution request or unexpected condition requires engineering guidance.

Common RFIs on residential projects include:

  • Requests to substitute a specified structural member with a different size or grade
  • Queries about connection details at junctions not fully detailed in the drawings
  • Requests for engineering guidance when unexpected soil conditions are encountered during excavation
  • Queries about the structural implications of a variation requested by the homeowner
  • Requests for confirmation that a proposed construction methodology is structurally acceptable

A structural engineer who responds to RFIs promptly - within 24 to 48 hours for urgent site queries - keeps the construction programme moving. An engineer who is slow to respond creates programme delays that cost the builder time and the homeowner money. Confirm the RFI process with the structural engineer before construction commences - how RFIs should be submitted, who to contact for urgent queries and what the expected response time is.

Questions to ask your structural engineer before construction starts

Have you reviewed the geotechnical investigation report and confirmed the footing design matches the soil classification across the full building footprint?

Have you coordinated your structural drawings with the architect's documentation - are there any contradictions that need to be resolved before construction commences?

Are the structural drawings incorporated into the building permit the current version?

Will you conduct a pre-construction site visit before the slab commences - particularly for our site's specific conditions?

What are the hold points during construction where your inspection or certification is required before the builder can proceed?

How should the builder submit RFIs to you during construction and what is your expected response time?

Will you attend the slab inspection and the frame inspection in person or will you be certifying remotely based on the builder's documentation?

Are there any other structural inspections required for our project beyond slab and frame stage?

If unexpected site conditions are discovered during excavation who should be contacted and what is the process for revising the footing design?

What documentation will you provide at each inspection stage - and will copies be provided to us as the homeowner?

What to do if your structural engineer is not providing these checks

If the engineer has not reviewed the geotechnical report before the footing design was finalised - request confirmation in writing that the footing design matches the soil classification

If the structural and architectural documentation has not been coordinated - request a written confirmation from both the engineer and the architect that the documentation is coordinated before the building permit is lodged

If no pre-construction site visit has been offered on a complex site - request one and confirm in writing whether the engineer considers a site visit necessary for your project conditions

If the builder is proceeding to pour the slab without a confirmed inspection - stop the pour and contact the building certifier and structural engineer immediately

If the builder is proceeding to close the frame without a confirmed inspection - stop and contact the building certifier and structural engineer

If RFIs are not being responded to within 48 hours on urgent site matters - escalate to the principal of the engineering firm and document the delay in writing

If you are not receiving inspection certificates at each hold point - request them in writing from the building certifier before the associated progress payment falls due

Red flags

Warning signs to watch for

  • Structural engineer has not reviewed the geotechnical report before the footing design was finalised - footing may not match the actual soil classification
  • No pre-construction site visit offered or conducted on a complex, sloped, coastal or reactive clay site
  • Builder proceeds to pour the slab without confirming the inspection hold point has been passed
  • Builder proceeds to close the frame without confirming the frame inspection has been passed
  • Structural engineer does not attend or certify the slab and frame inspections - no construction stage engagement at all
  • RFI responses take more than 48 hours for urgent site queries - programme delays and potential for builder to proceed without engineering guidance
  • Homeowner does not receive inspection certificates at each hold point - no documentary evidence that inspections were passed
  • Builder substitutes structural members without submitting an RFI to the structural engineer - unreported structural substitutions
  • Structural drawings in the building permit are a different version from the drawings the builder is constructing from
  • Engineer of record changes between design and construction stage without notification - continuity of engineering knowledge is lost

BUILTLY and lasting project records

The structural engineer's pre-construction checks and stage inspection certifications are among the most important documents in any residential construction project - and among the least likely to be preserved after the project is complete. A future owner, renovator or insurer who can access the original stage inspection certificates, geotechnical report and structural engineering drawings for a completed home has a level of transparency about the structural integrity of the building that self-reported project records cannot provide.

BUILTLY is building a record of completed Australian homes that credits the builder, architects, designers and trades behind each one.

For more on structural engineering and construction documentation, see our guides on How to Evaluate a Structural Engineer's Work in Australia, Building Specification Australia, What Is a Building Contract in Australia and Certificate of Currency Australia.

You may also find it useful to read Building a House Checklist Australia, How Long Does It Take to Build a House in Australia, How to Research a Builder Before Signing a Contract, Builder Complaints and Disputes Australia and What Verified Build Work Means.

Frequently asked questions

What does a structural engineer check before construction starts?

Before construction commences, a structural engineer should review the geotechnical investigation report to confirm the footing design matches the site's soil classification, coordinate their structural drawings with the architect's documentation to resolve any contradictions, confirm the structural drawings in the building permit are the current version and conduct a pre-construction site visit on complex or unusual sites. They should also confirm the hold point inspection schedule with the builder and establish the RFI process for construction queries. These pre-construction checks are the foundation of the construction-phase structural engineering service - without them the engineer's drawings may not reflect the actual site conditions.

What is a structural engineer hold point inspection?

A hold point inspection is a mandatory inspection at a defined stage of construction where the structural engineer - or a building certifier acting on the engineer's documentation - must confirm that the work completed to that point meets the structural specification before construction can proceed to the next stage. The two primary hold point inspections in residential construction are the slab or base stage inspection - conducted before the concrete is poured - and the frame stage inspection - conducted before the frame is closed by external cladding. Required inspections vary by state, building type and approval conditions, so confirm the stages with your building surveyor or certifier. A builder who proceeds past a hold point without the inspection being passed is in breach of the building permit conditions.

What happens at a slab stage structural inspection?

At the slab stage inspection the structural engineer or certifier confirms that the excavation depth and footing dimensions match the structural drawings, the reinforcement bar size, spacing and placement match the structural specification, the reinforcement cover meets the specification, any thickened edge beams and pad footings are correctly positioned and any waffle pod layout matches the drawings. The slab inspection is conducted before the concrete is poured because once the concrete is in place the reinforcement is permanently concealed. Errors discovered after the pour require coring, cutting or in severe cases complete demolition and reconstruction of the slab.

Can the builder proceed if the structural engineer has not passed the inspection?

No - the builder must comply with any statutory inspections and approval conditions, as well as any engineering hold points agreed in the contract. A builder who proceeds past a hold point without the inspection being passed is in breach of the building permit conditions and risks having the work required to be exposed or demolished. If your builder is indicating they intend to proceed without a completed inspection - or has already done so - contact the building certifier and the relevant state building regulator immediately. Request the inspection record promptly, and check your contract and state payment rules before withholding any payment.

What should I do if I am not receiving inspection certificates from the structural engineer?

Request them in writing from the building certifier - not just from the builder or engineer. The certifier handles statutory inspections; whether a progress payment is due depends on your building contract and state law. Make receiving the inspection certificate a condition of releasing each progress payment in the building contract. If the certifier cannot confirm an inspection has been passed, get advice before paying or withholding the payment. A builder who requests progress payment for a stage that has not been inspected and certified is requesting payment for unverified work.