Common Plumbing Issues in New Builds: What to Watch For

Last updated: October 2026

Plumbing defects are among the most common and most costly issues discovered in new residential buildings in Australia. Waterproofing failures, incorrectly graded drainage, inadequate hot water pressure, noisy pipes and leaking connections are all regularly identified during defects liability period inspections - and some are not discovered until years after handover when the damage they have caused is extensive and expensive to rectify. Understanding what the most common plumbing issues are, when they are most likely to be identified and what to do when they are found is practical knowledge for any homeowner taking possession of a new home in Australia. See also Plumbing Compliance Certificates Australia, What Plumbing Work Requires Certification Australia, and the complete guide to building a house in Australia.

Why plumbing issues are common in new builds

New residential construction involves significant plumbing complexity - water supply, hot water, drainage, stormwater, gas and waterproofing all installed in a compressed construction programme under time and cost pressure. Several factors make plumbing defects more likely in new builds than in established homes:

Compressed construction timelines

The plumbing rough-in stage - pulling pipes, setting drainage falls and positioning wet area waste outlets - happens early in the construction programme when the programme pressure is typically highest. Drainage falls that are slightly out of specification, waste outlet positions that are slightly off-centre and waterproofing that is applied too thinly under time pressure are all common consequences.

Multiple subcontractors

Plumbing in a new home involves multiple subcontractors - the rough-in plumber, the waterproofer, the tiler and the fit-off plumber are often different people or different firms. Coordination between them is the builder's responsibility but gaps in coordination - a tiler who does not notice the waste outlet is off-centre, a fit-off plumber who does not check the drainage grade before fixing the toilet - allow defects to be concealed before they are identified.

Waterproofing concealed by tiling

The most consequential plumbing-related defect in new builds - waterproofing failure - is concealed by tiles immediately after the waterproofing is applied. If the waterproofing was not inspected before tiling, a defect may not be discovered until water has been penetrating for months or years. See Building Inspections Australia.

Pressure testing not always rigorous

Water supply pipework should be pressure tested before walls are closed. If the pressure test is rushed or not conducted, small leaks at connections may not be identified until the wall lining is in place and water damage has occurred.

Common plumbing issues by location

LocationCommon issueCauseHow it manifests
Shower - floorWaterproofing failure at floor-to-wall junctionInsufficient membrane at junction, missing fibre reinforcement, membrane applied too thinlyWater penetration through adjacent wall or ceiling below - often not visible for months
Shower - wallsWaterproofing failure above tiling heightMembrane not extended to required height of 1800mm - water penetrates at grout lines above membraneWater damage to wall framing - visible as soft wall, paint bubbling or mould
Bathroom - generalGrout failure allowing water penetrationIncorrect grout type for wet areas, insufficient grout depth, movement crackingWater penetration through grout lines - damage to substrate and framing
ToiletIncorrectly positioned waste outletWaste outlet set at wrong position during rough-in - pan does not align correctlyToilet rocks, seal leaks, waste connection not properly seated
KitchenDrainage grade insufficientKitchen drain not graded correctly during rough-inSlow drainage, pooling in sink, odours from standing water in trap
LaundryTrough or washing machine connection leaksFitting not fully sealed, compression fitting not tightened correctly during fit-offWater under trough or washing machine - visible pooling or damage to floor
Hot water systemInadequate pressure or flow rateUndersized system for the home's demand, pressure reducing valve set incorrectlyInsufficient hot water, slow recovery, cold water in morning
Water supply - allWater hammer - banging pipesPipe not correctly clipped, water pressure too high, no hammer arrestorLoud banging when taps or appliances are turned off - particularly washing machines
Drainage - externalStormwater drainage insufficientStormwater system undersized or poorly gradedPooling on paving or in garden after rain - water against building
Gas - internalGas connection not fully sealedFitting not fully tightened during fit-off, thread sealant not appliedGas odour - safety risk requiring immediate action
Roof - flashingsPlumbing penetrations not correctly flashedVent pipes through roof not flashed correctly by plumber or rooferWater entry at penetration - water damage to ceiling and framing

Waterproofing failure - the most serious plumbing issue

Waterproofing failure is the single most common cause of post-construction defect claims in Australian residential construction - and the most expensive to rectify because the damage is typically extensive by the time it becomes visible.

How waterproofing failure occurs

The most vulnerable points in any wet area waterproofing system are the junctions - where the floor meets the wall, where the wall meets a door jamb or hob, and where the membrane meets any penetration such as a waste outlet or pipe. These junctions require specific treatment - fibre mesh reinforcement embedded in the membrane and additional membrane coverage - to prevent cracking and separation as the building moves through thermal and moisture cycles.

Waterproofing failure at junctions typically results from:

  • Insufficient membrane application at the junction - membrane applied too thinly to achieve the required film thickness
  • Missing fibre reinforcement at junctions - the mesh that bridges the junction and prevents cracking is omitted
  • Membrane applied over a dusty or contaminated substrate - adhesion is compromised
  • Membrane applied before the substrate has fully cured - moisture in the substrate causes adhesion failure
  • Tiling commencing before the membrane has fully cured - foot traffic damages the membrane before it has achieved full strength

How waterproofing failure manifests

Waterproofing failure is rarely immediately visible. Water penetrating through a failed membrane in a shower floor travels along the substrate and framing before becoming visible as damp patches, soft walls, paint bubbling or mould - typically in an adjacent room, the room below or at the base of the wall beside the shower. By the time it is visible, the water has often been penetrating for months.

What rectification involves

Rectifying waterproofing failure typically requires removing all tiles from the affected area, removing the failed membrane, preparing the substrate and applying new compliant waterproofing before retiling. This is a major and expensive rectification - typically $8,000 to $25,000 for a single bathroom depending on the extent of the damage and whether structural elements have been affected.

Prevention: The waterproofing inspection - conducted by the building certifier before tiling commences - is the primary prevention mechanism. Waterproofing failure is also one of the most common defects identified at practical completion. See the companion guide Plumbing Compliance Certificates Australia.

Hot water issues in new builds

Hot water problems are among the most commonly reported issues during the defects liability period in new homes - and among the most frustrating to live with while they are being resolved.

Undersized hot water system

The most common hot water issue is a system that is undersized for the home's demand. A hot water system specified for a two-bathroom home may be inadequate for a four-bathroom home with multiple simultaneous users. Confirm with the builder that the hot water system specification matches the home's bathroom count and anticipated occupancy before the contract is signed.

Pressure reducing valve set incorrectly

Australian water supply mains pressure varies and may exceed the safe operating pressure of the home's plumbing system. A pressure reducing valve - PRV - is installed to regulate the supply pressure to a safe level. If the PRV is set too low, hot water flow rates are inadequate. If set too high, there is a risk of pipe damage and premature fixture failure. Confirm the PRV setting with the plumber at handover.

Tempering valve not set correctly

All new residential hot water systems in Australia must include a tempering valve that limits the hot water temperature delivered to bathroom fixtures to 50°C - preventing scalding. If the tempering valve is not correctly set or is faulty, the delivered temperature may be too hot, creating a scalding risk, or too cool, creating a Legionella risk. Confirm the tempering valve setting at handover.

Expansion control valve

All hot water systems require an expansion control valve that releases water when the system pressure increases with heating. If the expansion control valve is not installed or is faulty, system pressure builds to dangerous levels. Confirm the expansion control valve is installed and operational at handover.

Water hammer - noisy pipes

What causes water hammer

Water hammer - the loud banging or thudding sound that occurs when taps or appliances are turned off - is one of the most commonly reported plumbing complaints in new builds and one of the easiest to prevent during construction. Water hammer occurs when flowing water is suddenly stopped - by closing a tap, a solenoid valve in a washing machine or dishwasher, or a float valve in a toilet cistern. The momentum of the moving water has nowhere to go and creates a pressure wave that travels through the pipework, creating the banging sound.

How it should be prevented during construction

  • Pipes should be correctly clipped to the framing at defined intervals - unclipped pipes move under pressure change and amplify the sound
  • Supply pressure should be regulated to an appropriate level through the PRV - excessively high supply pressure worsens water hammer
  • Hammer arrestors - small devices that absorb the pressure wave - should be installed at appliance connections where solenoid valves are present

What to do if water hammer is present

Report water hammer to the builder during the defects liability period. The builder is obligated to rectify it. Solutions range from adjusting the PRV setting - quickest fix - to installing hammer arrestors - more effective for severe cases - to accessing and clipping unsecured pipework - most disruptive but necessary if pipes are not correctly secured. See Builder Warranties Australia, Builder Complaints and Disputes Australia, and what to do if defects appear after handover.

Drainage issues in new builds

Insufficient drainage grade

All drainage pipework must be installed at a minimum fall - gradient - that allows waste and water to flow freely to the sewer without blocking. The minimum fall for most drainage is 1 in 40 - 25mm fall per metre of pipe. Drainage installed with insufficient fall drains slowly, allows solids to settle and creates recurring blockages and odour problems.

Insufficient drainage grade is almost always a rough-in error - the drainage was not installed at the correct fall during the rough-in stage. It is very difficult to rectify after the slab is poured or the floor is finished without significant demolition.

Incorrectly positioned waste outlets

Waste outlets - the drainage connection point for toilets, showers, baths and basins - must be positioned precisely during the rough-in stage. If a toilet waste outlet is even 20mm from the correct position, the toilet pan will not seat correctly and the waste seal may not be effective. This is a rough-in error that becomes a permanent problem if not identified before the slab is poured. See What a Structural Engineer Checks Before Construction Starts.

Stormwater drainage issues

Stormwater drainage from paving, roofs and garden areas must be correctly designed and installed to prevent water pooling against the building. Pooling water against the building creates waterproofing risk, foundation moisture issues and in extreme cases flooding. Confirm with the builder that stormwater drainage has been designed by a civil or hydraulic engineer and that the drainage system has been installed and tested before landscaping covers it.

When to identify plumbing issues

See also Documents Your Builder Must Provide at Each Stage Australia and Building a House Checklist Australia.

StageWhat to checkHow to check
Pre-slab - rough-in inspectionWaste outlet positions, drainage grade, pipe routingIndependent building inspector before concrete is poured
Pre-lining - waterproofing inspectionWaterproofing membrane correctly applied at all junctions and to required heightBuilding certifier inspection - mandatory hold point before tiling
Lock-up inspectionExternal drainage, stormwater routing, roof penetration flashingsIndependent building inspector
Pre-handover defect inspectionAll plumbing fixtures, hot water pressure and temperature, drainage flow rates, water hammer, visible leaksIndependent building inspector - commissioned by homeowner
3-month post-handover checkGrout condition in wet areas, water hammer, drainage flow rates, hot water performanceHomeowner inspection - report defects to builder in writing
12-month defects liability inspectionWaterproofing performance, grout integrity, all fixture operation, drainage performanceIndependent building inspector - before defects liability period expires

Pre-handover plumbing inspection checklist

Run all showers for five minutes and check for any leaks at connections, floor wastes and wall junctions

Flush all toilets multiple times - confirm flush is complete, cistern refills correctly and no rocking or movement at base

Run all basin and kitchen taps - confirm hot and cold water, adequate flow rate and no dripping after closing

Check under all vanity units and kitchen sink - confirm no moisture or water staining indicating leaks at connections

Check hot water temperature at all bathroom outlets - confirm tempering valve is set correctly at approximately 50°C

Check water pressure at showers and taps - confirm adequate flow rate under simultaneous use

Run the washing machine through a complete cycle - confirm no water hammer and no leaks at connection

Run the dishwasher through a complete cycle - confirm drainage and no water hammer

Check all external stormwater outlets - confirm they are clear and draining freely

Check all visible drainage in laundry and bathrooms - confirm draining freely with no gurgling indicating drainage grade issues

Confirm the plumbing compliance certificate has been provided - request it if not

What to do if plumbing issues are not fixed

See also How to Research a Builder Before Signing a Contract.

Report every plumbing defect to the builder in writing - email with photographs and specific description of the issue, location and when it was first observed

Confirm the builder has received and acknowledged the defect report - follow up if no acknowledgement within 48 hours

Set a reasonable rectification deadline in writing - typically 14 to 21 days for non-urgent defects, immediate for safety issues such as gas leaks or significant water leaks

If the builder does not rectify within the agreed timeline - send a formal written notice requesting rectification within a further defined period

If rectification is still not forthcoming - contact the relevant state building regulator: QBCC in Queensland, Building Commission NSW in NSW, BPC in Victoria

For significant waterproofing failures - engage an independent building inspector to prepare a formal defect report that documents the extent of the damage and the rectification required

For disputes that cannot be resolved through the builder - escalate to the relevant state tribunal: QCAT in Queensland, NCAT in NSW, VCAT in Victoria

Do not attempt to repair plumbing defects yourself without the builder's written agreement - self-repair without agreement may affect your rights under the defects liability provisions

Confirm the defects liability period expiry date and ensure all defects are reported in writing before it expires

Red flags

Builder refuses to arrange a waterproofing inspection before tiling commences - the inspection is a mandatory hold point
Builder cannot provide plumbing compliance certificate at handover
Water hammer present immediately after handover - indicates pipes not correctly secured or PRV set too high
Hot water temperature at bathroom outlets significantly above 50°C - tempering valve not correctly set
Slow drainage from any fixture immediately after handover - drainage grade issue from rough-in stage
Grout cracking or tile movement in wet areas within the first three months - substrate movement or waterproofing failure
Builder is unresponsive to written defect reports during the defects liability period
Builder attributes plumbing defects to homeowner use rather than construction defects - without evidence
Builder attempts to charge for rectification of defects that occurred during construction - defects liability period applies
Mould appearing on walls adjacent to wet areas within the first year - likely waterproofing failure

BUILTLY and lasting project records

Plumbing compliance certificates, waterproofing inspection certificates and defect rectification records are among the most practically important documents for any completed residential property. A future owner, renovator or insurer who can access the original plumbing compliance documentation and the defect history for a completed home has independently verifiable information about the quality and integrity of the plumbing installation that self-reported project records cannot provide.

BUILTLY is building a record of completed Australian homes that credits the builder, architects, designers and trades behind each one.

BUILTLY is building a record of completed Australian homes that credits the builder and specialist trades behind each one.

Frequently asked questions

What are the most common plumbing issues in new homes in Australia?

The most common plumbing issues in new Australian homes are waterproofing failure in wet areas - particularly at floor-to-wall junctions in showers - insufficient drainage grade causing slow drainage, incorrectly positioned waste outlets causing toilet alignment problems, water hammer from unsecured pipes or incorrect supply pressure, hot water system undersizing or incorrect tempering valve settings and grout failure in wet areas allowing water penetration. Waterproofing failure is the most serious and most expensive - by the time it becomes visible the damage is typically extensive and rectification costs $8,000 to $25,000 or more per bathroom.

How do I check for plumbing defects before handover?

Run all showers for five minutes and check for leaks. Flush all toilets multiple times. Run all taps and check hot water temperature and flow rate. Check under all vanity units and the kitchen sink for moisture or water staining. Run the washing machine and dishwasher through complete cycles and check for water hammer. Check all external stormwater outlets. Confirm drainage is flowing freely in all bathrooms and the laundry. Commission an independent building inspector to conduct a formal pre-handover inspection - an independent inspector identifies defects that an untrained eye misses and the formal report provides documentation for defect rectification requests.

What should I do if my new home has a plumbing defect?

Report every plumbing defect to the builder in writing - email with photographs and a specific description of the issue, location and when it was first observed. Set a reasonable rectification deadline in writing. If the builder does not rectify within the agreed timeline, send a formal written notice. If rectification is still not forthcoming, contact the relevant state building regulator - QBCC in Queensland, Building Commission NSW in NSW, BPC in Victoria. For significant defects, engage an independent building inspector to prepare a formal defect report. Do not attempt to repair plumbing defects yourself without the builder's written agreement - self-repair may affect your rights under the defects liability provisions.

How long does a builder have to fix plumbing defects in Australia?

The defects liability period - typically 12 months under the building contract - is the period during which the builder is contractually obligated to rectify defects that become apparent after handover. Statutory warranty periods under state building legislation provide additional protection - 6 years for major defects in NSW and Queensland, 10 years in Victoria. The builder must rectify plumbing defects reported during the defects liability period within a reasonable time - typically 14 to 21 days for non-urgent defects, immediately for safety issues. Confirm the defects liability period expiry date and ensure all defects are reported in writing before it expires.

Is waterproofing failure covered by home warranty insurance in Australia?

Waterproofing failure that results from defective work - incorrect application, missing membrane at junctions or insufficient film thickness - is a structural defect covered by the statutory warranty provisions in most Australian states. If the builder refuses to rectify and becomes insolvent, home warranty insurance covers the cost of rectification up to the insured limit. The key requirement is that the defect must be reported during the applicable warranty period - 6 years in NSW and Queensland, 10 years in Victoria for major defects. Document all waterproofing defects in writing as soon as they are identified and report them to the builder immediately.